Default How Long to Install a Lift?

There is no step-free access to the Jubilee Line at London Bridge from
24 February to mid-August while a lift is being replaced. That's about
6 months. Given that the lift shaft is already in place, could the job
not be done much more quickly?

--
John Ray

  #2   Report Post  
Old March 24th 15, 04:17 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Mar 2015
Posts: 1
Default How Long to Install a Lift?

Latest generation Kone lifts have a good reputation for reliability.


The "works" is all in the shaft, or "hoistway" to use the technical term.

This brochure from Kone US gives more details, although in a building context

http://cdn.kone.com/www.kone.us/Imag...evator.pdf?v=2

Ken


On 2015-03-23 13:49:35 +0000, Paul Corfield said:

On Mon, 23 Mar 2015 10:14:14 +0000, John Ray wrote:

There is no step-free access to the Jubilee Line at London Bridge from
24 February to mid-August while a lift is being replaced. That's about
6 months. Given that the lift shaft is already in place, could the job
not be done much more quickly?


The design of the replacement lift is very different from the one it
replaces AIUI. I believe the new lifts are machine room less lifts.
There was a recent TfL funding paper about this.

here is an excerpt from the paper about scope. There was no more
detail than this.

• Replacement of nine hydraulic lifts with KONE ‘machine-roomless’
traction units with gearless drive in line with the Lifts and
Escalators Strategy.
• Project management of Capex interventions for the 20 year
contract life until 2034.
• Enabling works including modifications to lift shafts and
improvements to ‘ancillary’ services.


  #3   Report Post  
Old March 29th 15, 01:25 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Jan 2005
Posts: 26
Default How Long to Install a Lift?

On Monday, 23 March 2015 13:49:35 UTC, Paul Corfield wrote:
On Mon, 23 Mar 2015 10:14:14 +0000, John Ray wrote:

There is no step-free access to the Jubilee Line at London Bridge from
24 February to mid-August while a lift is being replaced. That's about
6 months. Given that the lift shaft is already in place, could the job
not be done much more quickly?


The design of the replacement lift is very different from the one it
replaces AIUI. I believe the new lifts are machine room less lifts.
There was a recent TfL funding paper about this.

here is an excerpt from the paper about scope. There was no more
detail than this.

* Replacement of nine hydraulic lifts with KONE 'machine-roomless'
traction units with gearless drive in line with the Lifts and
Escalators Strategy.
* Project management of Capex interventions for the 20 year
contract life until 2034.
* Enabling works including modifications to lift shafts and
improvements to 'ancillary' services.

--
Paul C


So it is planned work then. That leaves me puzzled about why on the Tube map London Bridge has not lost its Jubilee line wheelchair symbol during these works, whereas other stations such as Kilburn lost their wheelchair symbol during the period they didn't have step free access. Anyone know why London Bridge is being treated differently?


Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
London's best lift John Rowland London Transport 25 March 23rd 08 09:41 AM
New Adobe Acrobat reader - should I install? John Rowland London Transport 7 July 3rd 07 03:17 PM
Wheelchair access lift [email protected] London Transport 0 February 28th 07 01:30 PM
Jubilee Line lift at Stratford John Rowland London Transport 4 December 27th 06 01:19 AM
Waterloo & City Line Car Lift Operation JMUpton2000 London Transport 21 April 7th 06 07:29 PM


All times are GMT. The time now is 05:36 AM.

Powered by vBulletin®
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 London Banter.
The comments are property of their posters.
 

About Us

"It's about London Transport"

 

Copyright © 2017