TfL have announced a follow on order for Electrostars, mainly for 4th
cars for their North London Railway fleet:
http://www.tfl.gov.uk/corporate/medi...ntre/5432.aspx

U

--
http://londonconnections.blogspot.com/


  #2   Report Post  
Old July 4th 07, 03:21 PM posted to uk.transport.london,uk.railway
external usenet poster
 
First recorded activity at LondonBanter: Jul 2003
Posts: 634
Default North London Line goes 4-car in early 2011

Mr Thant wrote:
TfL have announced a follow on order for Electrostars, mainly for 4th
cars for their North London Railway fleet:
http://www.tfl.gov.uk/corporate/medi...ntre/5432.aspx


I could never understand why they didn't order four-car units for the North
London line from the outset. You only have to look at the loadings on the
313s to see that additional capacity was desperately needed.


  #3   Report Post  
Old July 4th 07, 03:48 PM posted to uk.transport.london,uk.railway
external usenet poster
 
First recorded activity at LondonBanter: Nov 2003
Posts: 559
Default North London Line goes 4-car in early 2011


"Jack Taylor" wrote in message
...
Mr Thant wrote:
TfL have announced a follow on order for Electrostars, mainly for 4th
cars for their North London Railway fleet:
http://www.tfl.gov.uk/corporate/medi...ntre/5432.aspx


I could never understand why they didn't order four-car units for the

North
London line from the outset. You only have to look at the loadings on the
313s to see that additional capacity was desperately needed.

How much platform lengthening will be needed? In most cases it will merely
involve reopening sections of platfrom which have been out of use for years,
but lengthening Willesden Junction high level looks as though it will be
expensive.

Peter


  #4   Report Post  
Old July 4th 07, 03:50 PM posted to uk.transport.london,uk.railway
external usenet poster
 
First recorded activity at LondonBanter: Mar 2007
Posts: 973
Default North London Line goes 4-car in early 2011

On Jul 4, 3:21 pm, "Jack Taylor" wrote:
I could never understand why they didn't order four-car units for the North
London line from the outset. You only have to look at the loadings on the
313s to see that additional capacity was desperately needed.


Some of the platforms aren't long enough though, and Network Rail's
timescale for lengthening them is 2010. TfL are presumably quite keen
to get new trains running ASAP, with the switch to longitudinal
seating giving a short term capacity boost.

U

--
http://londonconnections.blogspot.com/

  #5   Report Post  
Old July 4th 07, 04:23 PM posted to uk.transport.london,uk.railway
Kev Kev is offline
external usenet poster
 
First recorded activity at LondonBanter: Nov 2005
Posts: 221
Default North London Line goes 4-car in early 2011

On Jul 4, 3:50 pm, Mr Thant
wrote:
On Jul 4, 3:21 pm, "Jack Taylor" wrote:


with the switch to longitudinal seating giving a short term capacity boost.

Oh f**k, everybody's answer to cramming even more people onto trains.
Why don't they go the whole way and remove all the seats. Just when I
thought that it might be worth using the NLL.

Kevin




  #6   Report Post  
Old July 4th 07, 04:23 PM posted to uk.transport.london,uk.railway
external usenet poster
 
First recorded activity at LondonBanter: Jul 2003
Posts: 634
Default North London Line goes 4-car in early 2011

Peter Masson wrote:

How much platform lengthening will be needed? In most cases it will
merely involve reopening sections of platfrom which have been out of
use for years, but lengthening Willesden Junction high level looks as
though it will be expensive.


That's the main culprit. Quite a lot need little work other than
stripping/resurfacing/drainage cleaning. WJ is the difficult one to squeeze
another car length out of. Even SDO (to use the inner doors only of the end
cars) wouldn't work, due to the siting of the signalling.


  #7   Report Post  
Old July 4th 07, 04:25 PM posted to uk.transport.london,uk.railway
external usenet poster
 
First recorded activity at LondonBanter: Jul 2003
Posts: 529
Default North London Line goes 4-car in early 2011

On Jul 4, 7:48 am, "Peter Masson" wrote:

but lengthening Willesden Junction high level looks as though it will be
expensive.



I'd say lengthening Willesden Juunction high level looks as though it
will be horrendously expensive - possibly out of all proportion.

One hopes that such an extensive piece of work willl be done to allow
at least 8car (two units of of the proposed 4car Electrostars) if not
12car.


--
Nick


  #8   Report Post  
Old July 4th 07, 04:39 PM posted to uk.transport.london,uk.railway
external usenet poster
 
First recorded activity at LondonBanter: Sep 2006
Posts: 135
Default North London Line goes 4-car in early 2011

Wouldn't it be relatively cheap to lengthen the platforms even
further? With the high level of overcrowding now and even more
passengers using the route in the future, it seems like it will be
needed. 8 coaches seems like a good number indeed.

Longitudinal seating is simply needed on routes like this It might be
slightly less comfortable, but that's not what peak train travellers
will be thinking about. They're just happy to be able to get on.

  #9   Report Post  
Old July 4th 07, 04:48 PM posted to uk.transport.london,uk.railway
external usenet poster
 
First recorded activity at LondonBanter: Nov 2003
Posts: 559
Default North London Line goes 4-car in early 2011


"sweek" wrote in message
oups.com...
Wouldn't it be relatively cheap to lengthen the platforms even
further? With the high level of overcrowding now and even more
passengers using the route in the future, it seems like it will be
needed. 8 coaches seems like a good number indeed.

Getting a 4-coach platform length at Willesden High level will be expensive,
but do-able. To get 8 coaches here, because of the junction with the City
Goods Line, the only place is on a bridge over the WCML. To build it you'd
probably need a lengthy closure of the WCML.

Peter


  #10   Report Post  
Old July 4th 07, 04:54 PM posted to uk.transport.london,uk.railway
external usenet poster
 
First recorded activity at LondonBanter: Jul 2003
Posts: 529
Default North London Line goes 4-car in early 2011

On Jul 4, 8:48 am, "Peter Masson" wrote:

probably need a lengthy closure of the WCML.

Peter


Merely continue as today then )

--
Nick




Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Last class 378 goes 5 car [email protected] London Transport 8 February 18th 16 11:08 AM
Last class 378 goes 5 car eastender[_5_] London Transport 2 February 16th 16 11:00 PM
RAIB Investigation into an incident at Warren Street station, Victoria Line, London Underground, 11 July 2011 Mizter T London Transport 3 August 5th 11 04:49 PM
Four-car North London Line Dr. Sunil London Transport 3 October 27th 10 12:26 PM


All times are GMT. The time now is 10:48 AM.

Powered by vBulletin®
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 London Banter.
The comments are property of their posters.
 

About Us

"It's about London Transport"

 

Copyright © 2017