View Single Post
  #22   Report Post  
Old September 5th 11, 02:05 PM posted to uk.transport.london
[email protected] rosenstiel@cix.compulink.co.uk is offline
external usenet poster
 
First recorded activity at LondonBanter: Sep 2008
Posts: 4,877
Default Stations overcrowding report finalised

In article ,
(Paul Scott) wrote:

There will be some simultaneous movements possible, because incoming
ELL/SLL trains will run past the existing stopping point to a new
platform extended out to the current centre track of 3. The new
platform will then become P2, the existing WLL platform will become a
bay and be renumbered as P1.


That isn't consistent with the reports that a Cambridge solution will be
adopted. For that to be the case there would need to be a new scissors
crossover halfway along platform 2 connecting to the through road.

--
Colin Rosenstiel