Default Chiltern to Paddington

As most people here must know, Chiltern runs one service a day, M-F,
to Paddington. It's run mainly for maintaining driver route knowledge
for the occasions when Chiltern services are diverted to Paddington.

It's not quite a parly service, as it runs at a convenient time, five
days a week, but it's also not promoted and little used other than by
rail enthusiasts (the few passengers are all sole males with cameras).
And, yes, I was one of those this week, and here's the evidence:
https://www.flickr.com/photos/reclin...57654494380303

But it got me wondering if Chiltern could or should run more services
into Paddington? Chiltern's services are growing steadily, with 2 tph
Oxford services being added soon. The two-track route into Marylebone
is congested, as are Marylebone's six platforms. Would it be possible
to run, say, 2 tph into Paddington? There's obviously many
constraints, including:

- the single track sections on the neglected former main line from
South Ruislip to Old Oak Common, which also sees occasional freight
trains

- the flat Old Oak Common West Junction to the GW relief lines

- capacity on the relief lines into Paddington

- Paddington platform availability.

But might there still be room for a limited number of Chiltern
services, maybe even at peak times? Once Crossrail starts, there will
be more room in Paddington itself, but what about on the approach
lines?