In message , Chris Game
writes
If the line went into overload
protection at a fraction of what it should have done, a simple test
of the line during commissioning (at 50% of rating) would have shown
this.


I wonder how you test 2500 amp circuits on load when a large section of
south London only draws half of that. What's the dummy-load going to
look like?
--
Roland Perry