View Single Post
  #13   Report Post  
Old February 15th 07, 07:31 PM posted to uk.transport.london
Paul Corfield Paul Corfield is offline
external usenet poster
 
First recorded activity at LondonBanter: Jul 2003
Posts: 3,995
Default Victoria line today around 1030

On Thu, 15 Feb 2007 20:21:18 +0000, Tom Anderson
wrote:

On Thu, 15 Feb 2007, Paul Corfield wrote:

On Thu, 15 Feb 2007 10:21:58 +0000, Tom Anderson
wrote:

On Wed, 14 Feb 2007, Paul Corfield wrote:

On Wed, 14 Feb 2007 16:56:50 +0000, Paul Terry
wrote:

In message , Tom
Anderson writes

Then got an announcement: "this train is being held here, as there
is planned engineering work at Victoria; the engineers will be on
the line for about ten minutes".

Secondly, am i right in assuming the "planned" was a mistake?

Sounds like it: engineering work, yes, but not planned!

Planned in the sense that LU allowed them on to the tracks but not
planned in the sense of a long planned possession.

Genius! So is there also unplanned engineering work, where the navvies
just bundle past the platform staff and fix things before anyone can stop
them, then?


There was a signal failure that was traced to a problem with the cables.
In such circumstances it is essential that track staff are allowed on to
the track to investigate, identify the fault and then repair or replace
the cable. Obviously no one plans to have a failure so any requirement
for a possession to effect a repair is unplanned !


Maybe they should - then they could have all the failures at night, when
it wouldn't disrupt the service.

Hmm. Seriously, that might work. If there are known conditions that tend
to push almost-failed systems into failure, such as rapid switching, power
spikes, brownouts, vibration, etc, then it might be possible to generate
those deliberately during maintenance time to root out weedy components.
Although if this is possible, i would imagine it's already being done.


Most of the things you suggest would probably require trains to run
which rather defeats the main object of engineering hours. There is a
lot of inspection and checking that goes on to make sure rails and track
components are fit for use as well as permanently repairing things (like
power and signal cables) which might have had a temporary fix during
traffic hours. In addition certain track repairs to remove temporary
speed restrictions can only happen at night - the same applies to
swapping things out like defective blockjoints and trainstops.

Oh and then you've got to add on upgrade related works on top of all of
that.

If you did some of the tests you suggest and they caused a serious
failure it is possible that a line would not start on time and there'd
be an overrun of engineering hours which for certain lines can wreck the
service for many hours. Overruns are also hugely unpopular with
passengers.

Cheers for the info once again, Mr C.


OK.
--
Paul C


Admits to working for London Underground!