London Banter

London Banter (https://www.londonbanter.co.uk/forum.php)
-   London Transport (https://www.londonbanter.co.uk/london-transport/)
-   -   Thameslink programme to go ahead "in it's entirety" (https://www.londonbanter.co.uk/london-transport/11492-thameslink-programme-go-ahead-its.html)

Mizter T November 25th 10 09:37 AM

Thameslink programme to go ahead "in it's entirety"
 
Amongst a number of points covered in SoS Hammond's announcement this
morning was this one:

---quote---
Today, I can confirm we will fund and deliver the Thameslink programme in
its entirety, virtually doubling the number of north-south trains running
through central London at peak times. But the original programme for the
rebuilding of London Bridge was always ambitious, with substantial risks
around delivery, and operation of existing services, during construction.
To reduce these risks, we have re-profiled the delivery of the programme to
achieve completion in 2018. This will enable Network Rail to make further
efficiencies to their design and delivery programme.
---/quote---

Source:
http://www.dft.gov.uk/press/speeches...ammond20101125

So, it appears as though the whole shebang will go ahead as originally
envisaged, i.e. including Key Output 2 (of which the extensive Bermondsey
dive-unders on the approaches to London Bridge are a part, for instance).


1506[_2_] November 25th 10 10:59 AM

Thameslink programme to go ahead "in it's entirety"
 
On Nov 25, 10:37*am, "Mizter T" wrote:
Amongst a number of points covered in SoS Hammond's announcement this
morning was this one:

---quote---
Today, I can confirm we will fund and deliver the Thameslink programme in
its entirety, virtually doubling the number of north-south trains running
through central London at peak times. But the original programme for the
rebuilding of London Bridge was always ambitious, with substantial risks
around delivery, and operation of existing services, during construction.
To reduce these risks, we have re-profiled the delivery of the programme to
achieve completion in 2018. *This will enable Network Rail to make further
efficiencies to their design and delivery programme.
---/quote---

Source:http://www.dft.gov.uk/press/speeches...ts/hammond2010...

So, it appears as though the whole shebang will go ahead as originally
envisaged, i.e. including Key Output 2 (of which the extensive Bermondsey
dive-unders on the approaches to London Bridge are a part, for instance).


Excellent news. And, given the circumstances, surprising. A good day
for railways of the UK's Southeast, and especially London.


Bruce[_2_] November 25th 10 12:32 PM

Thameslink programme to go ahead "in it's entirety"
 
"Mizter T" wrote:
Amongst a number of points covered in SoS Hammond's announcement this
morning was this one:
Today, I can confirm we will fund and deliver the Thameslink programme in
its entirety, virtually doubling the number of north-south trains running
through central London at peak times. But the original programme for the
rebuilding of London Bridge was always ambitious, with substantial risks
around delivery, and operation of existing services, during construction.
To reduce these risks, we have re-profiled the delivery of the programme to
achieve completion in 2018. This will enable Network Rail to make further
efficiencies to their design and delivery programme.
Source:
http://www.dft.gov.uk/press/speeches...ammond20101125

So, it appears as though the whole shebang will go ahead as originally
envisaged, i.e. including Key Output 2 (of which the extensive Bermondsey
dive-unders on the approaches to London Bridge are a part, for instance).



This is excellent news, and by far the most satisfying part of today's
announcement. The Thameslink project has recently been overshadowed
by its more glamorous relative, Crossrail, yet the economic and
environmental benefits that Thameslink will deliver to London and the
south east are no less significant.

There was real concern worry that the high cost of (1) remodelling
London Bridge to include additional though platforms and (2) the
Bermondsey dive-unders could have caused the project to be curtailed.
However, this budgetary problem has been solved by allowing an
additional two years to complete the project. This spreads the cost
over a greater number of financial years and allows more economic (and
less disruptive) methods of construction to be used at London Bridge.

All praise to the Thameslink project team who have succeeded in
gaining Ministerial approval for the whole of this vital if somewhat
unsexy project.


Bruce[_2_] November 25th 10 02:17 PM

Thameslink programme to go ahead "in it's entirety"
 
"Richard Hunt" wrote:

Mizter T wrote:
So, it appears as though the whole shebang will go ahead as
originally envisaged, i.e. including Key Output 2 (of which the
extensive Bermondsey dive-unders on the approaches to London Bridge
are a part, for instance).


Was the original "Thameslink 2000" project, as envisaged, ever
completed?



It was delayed.

Basically, Thameslink 2000 is what we are discussing.

Roy Badami November 25th 10 02:34 PM

Thameslink programme to go ahead "in it's entirety"
 
In article ,
Bruce wrote:
"Richard Hunt" wrote:

It was delayed.

Basically, Thameslink 2000 is what we are discussing.


Right. It was renamed "The Thameslink Programme" once the delays got
so long that the 2000 name was just too emabarassingly silly.

-roy

Roland Perry November 25th 10 02:51 PM

Thameslink programme to go ahead "in it's entirety"
 
In message , at 10:37:20 on
Thu, 25 Nov 2010, Mizter T remarked:
Amongst a number of points covered in SoS Hammond's announcement this
morning was this one:

---quote---
Today, I can confirm we will fund and deliver the Thameslink programme
in its entirety


Does that include the link-up with the GN line to Cambridge, or was that
air-brushed from the scheme long ago?

istr they were supposed to be lengthening platforms at Cambridge to take
12 cars, but I think they may have changed their mind and are doing an
island instead.
--
Roland Perry

Bruce[_2_] November 25th 10 03:14 PM

Thameslink programme to go ahead "in it's entirety"
 
(Roy Badami) wrote:
In article ,
Bruce wrote:
"Richard Hunt" wrote:

It was delayed.

Basically, Thameslink 2000 is what we are discussing.


Right. It was renamed "The Thameslink Programme" once the delays got
so long that the 2000 name was just too emabarassingly silly.



"Thameslink 2018" doesn't have quite the same ring to it. ;-)


[email protected] November 25th 10 03:27 PM

Thameslink programme to go ahead "in it's entirety"
 
Anyone know what the plans are for the remaining parts of the moorgate line
are? Will LU take them over eventually?

B2003


Roy Badami November 25th 10 03:40 PM

Thameslink programme to go ahead "in it's entirety"
 
In article ,
Bruce wrote:
Basically, Thameslink 2000 is what we are discussing.


Right. It was renamed "The Thameslink Programme" once the delays got
so long that the 2000 name was just too emabarassingly silly.


"Thameslink 2018" doesn't have quite the same ring to it. ;-)


So basically, we are today celebrating that Thameslink 2000 is only
delayed a further two years (now making it 18 years late) rather than
actually being cancelled :-/

-roy




Roy Badami November 25th 10 03:41 PM

Thameslink programme to go ahead "in it's entirety"
 
In article ,
Roland Perry wrote:
istr they were supposed to be lengthening platforms at Cambridge to take
12 cars, but I think they may have changed their mind and are doing an
island instead.


Cambridge has had 12-car Class 365 services to Kings Cross in the
morning peak for some time now.

-roy

Roland Perry November 25th 10 03:50 PM

Thameslink programme to go ahead "in it's entirety"
 
In message , at 16:14:35 on
Thu, 25 Nov 2010, Bruce remarked:
It was renamed "The Thameslink Programme" once the delays got
so long that the 2000 name was just too emabarassingly silly.


"Thameslink 2018" doesn't have quite the same ring to it. ;-)


2018 is obviously the year when Thameslink 2000 comes of age.
--
Roland Perry

Roland Perry November 25th 10 03:51 PM

Thameslink programme to go ahead "in it's entirety"
 
In message , at 16:41:58 on Thu,
25 Nov 2010, Roy Badami remarked:
istr they were supposed to be lengthening platforms at Cambridge to take
12 cars, but I think they may have changed their mind and are doing an
island instead.


Cambridge has had 12-car Class 365 services to Kings Cross in the
morning peak for some time now.


Isn't that being done by some sort of kludge, rather than lengthening
both platforms 1 & 4 so that all trains could be 12-car, as was
originally proposed?
--
Roland Perry

Paul Scott[_3_] November 25th 10 04:12 PM

Thameslink programme to go ahead "in it's entirety"
 


"Roland Perry" wrote in message
...
In message , at 10:37:20 on Thu,
25 Nov 2010, Mizter T remarked:
Amongst a number of points covered in SoS Hammond's announcement this
morning was this one:

---quote---
Today, I can confirm we will fund and deliver the Thameslink programme in
its entirety


Does that include the link-up with the GN line to Cambridge, or was that
air-brushed from the scheme long ago?


Yes it does, but its removal has only been presumed by the more pessimistic
posts here, and IIRC some equally pessimistic rail mag editorials.

This afternoons oral statement adds to what Mizter T posted above:

"I can also confirm today that we will fund and deliver the Thameslink
programme in its entirety, virtually doubling the number of north-south
trains running through central London at peak times. This huge investment
will link Sussex, Kent and Surrey, through central London, with
Hertfordshire, Bedfordshire and Cambridgeshire."

Paul S




Bruce[_2_] November 25th 10 04:29 PM

Thameslink programme to go ahead "in it's entirety"
 
(Roy Badami) wrote:
In article ,
Bruce wrote:
Basically, Thameslink 2000 is what we are discussing.

Right. It was renamed "The Thameslink Programme" once the delays got
so long that the 2000 name was just too emabarassingly silly.


"Thameslink 2018" doesn't have quite the same ring to it. ;-)


So basically, we are today celebrating that Thameslink 2000 is only
delayed a further two years (now making it 18 years late) rather than
actually being cancelled :-/



Given the appalling state in which labour left the public finances, I
think we are very lucky indeed that Thameslink is going ahead.

So yes, we are celebrating. ;-)


1506[_2_] November 25th 10 04:39 PM

Thameslink programme to go ahead "in it's entirety"
 
On Nov 25, 8:27*am, wrote:
Anyone know what the plans are for the remaining parts of the moorgate line
are? Will LU take them over eventually?

B2003


There is no obvious use for the extra pair from Farringdon to
Moorgate, sad really.

1506[_2_] November 25th 10 04:41 PM

Thameslink programme to go ahead "in it's entirety"
 
On Nov 25, 8:40*am, (Roy Badami) wrote:
In article ,

Bruce wrote:
Basically, Thameslink 2000 is what we are discussing. *


Right. *It was renamed "The Thameslink Programme" once the delays got
so long that the 2000 name was just too emabarassingly silly.


"Thameslink 2018" doesn't have quite the same ring to it. *;-)


So basically, we are today celebrating that Thameslink 2000 is only
delayed a further two years (now making it 18 years late) rather than
actually being cancelled :-/

Given the state of the UK economy, this is VERY good.

Mizter T November 25th 10 05:03 PM

Thameslink programme to go ahead "in it's entirety"
 

"1506" wrote:

On Nov 25, 8:27 am, wrote:

Anyone know what the plans are for the remaining parts of the moorgate
line
are? Will LU take them over eventually?


There is no obvious use for the extra pair from Farringdon to
Moorgate, sad really.


I think it's to be used at least in part as a stabling location for the new
(longer) S-stock - at the moment part of it is being used as a worksite
(storage etc) for the Farringdon Thameslink works - might also prove useful
(indeed could well be part of the plan) to utilise it in the same capacity
for Crossrail works too.


Mizter T November 25th 10 05:05 PM

Thameslink programme to go ahead "in it's entirety"
 

"Roland Perry" wrote:

In message , at 16:14:35
on Thu, 25 Nov 2010, Bruce remarked:

It was renamed "The Thameslink Programme" once the delays got
so long that the 2000 name was just too emabarassingly silly.


Hence the occasional 'Thameslink 3000' moniker!


"Thameslink 2018" doesn't have quite the same ring to it. ;-)


2018 is obviously the year when Thameslink 2000 comes of age.


Very good!

Mizter T November 25th 10 05:21 PM

Thameslink programme to go ahead "in it's entirety"
 

"Paul Corfield" wrote:

On Thu, 25 Nov 2010 16:27:42 +0000 (UTC), d wrote:

Anyone know what the plans are for the remaining parts of the moorgate
line
are? Will LU take them over eventually?


I thought something had been said in Modern Railways about the remaining
alignment (net of any incursions by Crossrail or Thameslink works) was
being considered as potential stabling sidings for LUL use. I might be
imagining it though!


I don't think you are, though I don't think I've ever read or heard anything
solid about it. From a layman's point of view it'd seems like a decent
location for some sidings.


Basil Jet[_2_] November 25th 10 05:28 PM

Thameslink programme to go ahead "in it's entirety"
 
On 2010\11\25 16:14, Bruce wrote:
(Roy Badami) wrote:
In ,
wrote:
"Richard wrote:

It was delayed.

Basically, Thameslink 2000 is what we are discussing.


Right. It was renamed "The Thameslink Programme" once the delays got
so long that the 2000 name was just too emabarassingly silly.



"Thameslink 2018" doesn't have quite the same ring to it. ;-)


How about "Thameslink's 2020 Vision"?

Google says that some one beat me to this gag in 2004, in a discussion
about how Thameslink 2000 would not be finished until 2015. So in the
last 6 years the timetable has only slipped by 3 years. At this rate,
the government will be announcing in 2028 that the project was completed
in 2027, even though nothing will have actually been done.

Basil Jet[_2_] November 25th 10 05:32 PM

Thameslink programme to go ahead "in it's entirety"
 
On 2010\11\25 18:21, Mizter T wrote:

"Paul Corfield" wrote:

On Thu, 25 Nov 2010 16:27:42 +0000 (UTC), d wrote:

Anyone know what the plans are for the remaining parts of the
moorgate line
are? Will LU take them over eventually?


I thought something had been said in Modern Railways about the remaining
alignment (net of any incursions by Crossrail or Thameslink works) was
being considered as potential stabling sidings for LUL use. I might be
imagining it though!


I don't think you are, though I don't think I've ever read or heard
anything solid about it. From a layman's point of view it'd seems like a
decent location for some sidings.


Given the value of land in the area, it's a decent location for pretty
much anything but sidings. There's a disused bay platform at Liverpool
Street behind shutters, so there can't be much need for extra track in
the area.

Mizter T November 25th 10 05:43 PM

Thameslink programme to go ahead "in it's entirety"
 

"Basil Jet" wrote:

On 2010\11\25 18:21, Mizter T wrote:

"Paul Corfield" wrote:

On Thu, 25 Nov 2010 16:27:42 +0000 (UTC), d wrote:

Anyone know what the plans are for the remaining parts of the
moorgate line are? Will LU take them over eventually?

I thought something had been said in Modern Railways about the remaining
alignment (net of any incursions by Crossrail or Thameslink works) was
being considered as potential stabling sidings for LUL use. I might be
imagining it though!


I don't think you are, though I don't think I've ever read or heard
anything solid about it. From a layman's point of view it'd seems like a
decent location for some sidings.


Given the value of land in the area, it's a decent location for pretty
much anything but sidings. [...]


I disagree - this is a two-track width railway bed in a cutting next to an
operational two-track railway, and the cutting is surrounded by buildings
already. I'm not trying to suggest that there couldn't be various clever
ways of fitting in some development into this space, but it's a rather
constrained linear location (/locations) which is hardly ideal for
development.

[...] There's a disused bay platform at Liverpool Street behind shutters,
so there can't be much need for extra track in the area..


AIUI the issue w.r.t. the new S-stock trains is that they're going to be too
long for several of the present stabling sidings that exist on the
sub-surface railway. I'm not sure if the bay platform at Liverpool Street
would be workable, and I rather doubt that it alone would satisfy the
apparent need.


Jim Chisholm November 25th 10 06:10 PM

Thameslink programme to go ahead "in it's entirety"
 
On 25/11/2010 16:51, Roland Perry wrote:
In message , at 16:41:58 on Thu,
25 Nov 2010, Roy Badami remarked:
istr they were supposed to be lengthening platforms at Cambridge to take
12 cars, but I think they may have changed their mind and are doing an
island instead.


Cambridge has had 12-car Class 365 services to Kings Cross in the
morning peak for some time now.


Isn't that being done by some sort of kludge, rather than lengthening
both platforms 1 & 4 so that all trains could be 12-car, as was
originally proposed?


The Island Platform at Cambridge is due to be opened in just over a
year. They've possessions booked, and it is needed for the proposed 12
car service to Liverpool St, trains for which are already being produced.

Jim

Ivor November 25th 10 06:10 PM

Thameslink programme to go ahead "in it's entirety"
 
On Thu, 25 Nov 2010 18:28:31 +0000, Basil Jet
wrote:

At this rate,
the government will be announcing in 2028 that the project was completed
in 2027, even though nothing will have actually been done.


How many times has the WCML upgrade been 'completed'?!!

Bruce[_2_] November 25th 10 07:26 PM

Thameslink programme to go ahead "in it's entirety"
 
Ivor wrote:
On Thu, 25 Nov 2010 18:28:31 +0000, Basil Jet
wrote:

At this rate,
the government will be announcing in 2028 that the project was completed
in 2027, even though nothing will have actually been done.


How many times has the WCML upgrade been 'completed'?!!



Actually, it has never been completed.

Network Rail reduced the scope of works and specification to such a
extent that the WCML upgrade may never be completed to anything close
to the original scope and specification.


D7666 November 25th 10 08:03 PM

Thameslink programme to go ahead "in it's entirety"
 
On Nov 25, 8:26*pm, Bruce wrote:

How many times has the WCML upgrade been 'completed'?!!


Actually, it has never been completed. *



Alternative answer : every Monday morning since 1967.

And upgraded starting every Friday night since 1967 .

--
Nick


Roy Badami November 25th 10 08:17 PM

Thameslink programme to go ahead "in it's entirety"
 
In article ,
Roland Perry wrote:
In message , at 16:41:58 on Thu,
Isn't that being done by some sort of kludge, rather than lengthening
both platforms 1 & 4 so that all trains could be 12-car, as was
originally proposed?


What kind of kludge? I thought I read here that some work (not sure
what) was done a while back to allow platform 1 to accommodate the
12-car trains.

I don't think the 12-car trains straddle platforms 1 & 4, if that's
what you mean?

-roy

Fat richard November 25th 10 09:16 PM

Thameslink programme to go ahead "in it's entirety"
 
On Nov 25, 10:37*am, "Mizter T" wrote:
Amongst a number of points covered in SoS Hammond's announcement this
morning was this one:

---quote---
Today, I can confirm we will fund and deliver the Thameslink programme in
its entirety, virtually doubling the number of north-south trains running
through central London at peak times. But the original programme for the
rebuilding of London Bridge was always ambitious, with substantial risks
around delivery, and operation of existing services, during construction.
To reduce these risks, we have re-profiled the delivery of the programme to
achieve completion in 2018. *This will enable Network Rail to make further
efficiencies to their design and delivery programme.
---/quote---

Source:http://www.dft.gov.uk/press/speeches...ts/hammond2010...

So, it appears as though the whole shebang will go ahead as originally
envisaged, i.e. including Key Output 2 (of which the extensive Bermondsey
dive-unders on the approaches to London Bridge are a part, for instance).


Well thats me twenty quid short, I had a bet going on the GN not
joining up and the stock not being the new generation of fixed
formation 8 / 12 cars. I thought A.T.O. had been officially poo
pooed ?

Richard

Paul Scott[_3_] November 25th 10 10:11 PM

Thameslink programme to go ahead "in it's entirety"
 
"Fat richard" wrote in message
...

Well thats me twenty quid short, I had a bet going on the GN not
joining up and the stock not being the new generation of fixed
formation 8 / 12 cars. I thought A.T.O. had been officially poo
pooed ?


Never more than educated speculation I think, based on the presumption many
people seem to have made 6 months ago that 'Conservatives = Guaranteed
Cuts' - so discussion centred on what was likely to give. The flames will
have been fanned because within NR people will have had to prepare options
for downgrades, but they presumably always hoped they wouldn't happen.

When one of the rail mags I get ran a piece on ATO being cancelled a while
back, the very next issue quoted a NR denial. Over the late summer when
posters here were suggesting the new signalling might be downgraded to only
16 tph, I searched and found that a contract had just been let to install
signalling to allow 24 tph.

Paul S


D7666 November 25th 10 10:17 PM

Thameslink programme to go ahead "in it's entirety"
 
On Nov 25, 10:16*pm, Fat richard wrote:

Today, I can confirm we will fund and deliver the Thameslink programme in
its entirety,


Well thats me twenty quid short, I had a bet going on the GN not
joining up and the stock not being the new generation of fixed
formation 8 / 12 cars. I thought A.T.O. had been officially poo
pooed ?



I was going for no GN link up too ... with that allowing less TPH so
no need for ATO.


mode cynic

Entirety .... ''the Thameslink programme in its entirety'' ....
yes ... now what /does/ that mean ... entirety at what point of
reference ?

At the point TL2000 morphed into TLP ? That can't be as some parts
have since been descoped from TLP eg 12car platforms at Kentish
Town, 25 kV wires to Blackfriars ... and no way was the depot ever
to be at Hornsey back then.

TLP has moved its own goalposts since TL2000.

Is it just possible there is some doublespeak here with ''entirety''
meaning ''what the DfT looked at this time round'' and some of the
rumours (like no ATO) might be facts ?


/ mode cynic

--
Nick






Jack Taylor November 25th 10 11:20 PM

Thameslink programme to go ahead "in it's entirety"
 
Paul Corfield wrote:
On Thu, 25 Nov 2010 16:27:42 +0000 (UTC), d
wrote:

Anyone know what the plans are for the remaining parts of the
moorgate line are? Will LU take them over eventually?


I thought something had been said in Modern Railways about the
remaining alignment (net of any incursions by Crossrail or Thameslink
works) was being considered as potential stabling sidings for LUL
use. I might be imagining it though!


The problem is access. The only real access route would be across the
existing, short stabling sidings at Farringdon - but that would approach the
Smithfield tunnels at a rather oblique angle.

As someone who daily suffers the problems of congestion between Baker Street
and Aldgate, due to too many trains being funnelled down into the City, I
had long been thinking whether there was any way of separating Moorgate
terminators at Farringdon and running them parallel down into the old
Thameslink platforms at Moorgate (possibly even reducing the number of
Aldgate terminators by, for example, turning all or some of the Uxbridges at
Moorgate). All armchair planning, of course, but I think that the tunnel
approach from the Farringdon direction rules out any serious use of the
remains of the branch, unless some extensive building work is carried out
beneath Smithfield to realign the tunnels.



Roland Perry November 26th 10 06:22 AM

Thameslink programme to go ahead "in it's entirety"
 
In message , at 21:17:40 on Thu,
25 Nov 2010, Roy Badami remarked:
Isn't that being done by some sort of kludge, rather than lengthening
both platforms 1 & 4 so that all trains could be 12-car, as was
originally proposed?


What kind of kludge? I thought I read here that some work (not sure
what) was done a while back to allow platform 1 to accommodate the
12-car trains.

I don't think the 12-car trains straddle platforms 1 & 4, if that's
what you mean?


Yes, that's what I meant; but I haven't seen any positive indications
either way (other than perhaps a lack of people commenting how they've
seen a 12-car in Platform 1 that didn't foul the x-over).
--
Roland Perry

Roland Perry November 26th 10 06:25 AM

Thameslink programme to go ahead "in it's entirety"
 
In message , at 19:10:08 on
Thu, 25 Nov 2010, Jim Chisholm remarked:

istr they were supposed to be lengthening platforms at Cambridge to take
12 cars, but I think they may have changed their mind and are doing an
island instead.

Cambridge has had 12-car Class 365 services to Kings Cross in the
morning peak for some time now.


Isn't that being done by some sort of kludge, rather than lengthening
both platforms 1 & 4 so that all trains could be 12-car, as was
originally proposed?


The Island Platform at Cambridge is due to be opened in just over a
year. They've possessions booked, and it is needed for the proposed 12
car service to Liverpool St, trains for which are already being produced.


If both 1 & 4 were usable by 12-car trains, perhaps they wouldn't need
such a long island. Do you know whether they've changed strategy, or
will 1 & 4 & the island all be capable of 12-car?
--
Roland Perry

Roland Perry November 26th 10 06:29 AM

Thameslink programme to go ahead "in it's entirety"
 
In message
, at
15:17:10 on Thu, 25 Nov 2010, D7666 remarked:
Entirety .... ''the Thameslink programme in its entirety'' ....
yes ... now what /does/ that mean ... entirety at what point of
reference ?

At the point TL2000 morphed into TLP ? That can't be as some parts
have since been descoped from TLP eg 12car platforms at Kentish
Town, 25 kV wires to Blackfriars ... and no way was the depot ever
to be at Hornsey back then.

TLP has moved its own goalposts since TL2000.

Is it just possible there is some doublespeak here with ''entirety''
meaning ''what the DfT looked at this time round'' and some of the
rumours (like no ATO) might be facts ?


I tend to agree with you. Wasn't there once a suggestion that to get
24tph you'd have needed island platforms at SPILL, with Bedpan and GN
trains using alternate sides?
--
Roland Perry

TimB[_2_] November 26th 10 07:16 AM

Thameslink programme to go ahead "in it's entirety"
 
On Nov 26, 7:25*am, Roland Perry wrote:
In message , at 19:10:08 on
Thu, 25 Nov 2010, Jim Chisholm remarked:

istr they were supposed to be lengthening platforms at Cambridge to take
12 cars, but I think they may have changed their mind and are doing an
island instead.


Cambridge has had 12-car Class 365 services to Kings Cross in the
morning peak for some time now.


Isn't that being done by some sort of kludge, rather than lengthening
both platforms 1 & 4 so that all trains could be 12-car, as was
originally proposed?


The Island Platform at Cambridge is due to be opened in just over a
year. They've possessions booked, and it is needed for the proposed 12
car service to Liverpool St, trains for which are already being produced..


If both 1 & 4 were usable by 12-car trains, perhaps they wouldn't need
such a long island. Do you know whether they've changed strategy, or
will 1 & 4 & the island all be capable of 12-car?
--
Roland Perry


1 is 12-car, 4 isn't.
Tim

1506[_2_] November 26th 10 09:24 AM

Thameslink programme to go ahead "in it's entirety"
 
On Nov 25, 6:03*pm, "Mizter T" wrote:
"1506" wrote:
On Nov 25, 8:27 am, wrote:


Anyone know what the plans are for the remaining parts of the moorgate
line
are? Will LU take them over eventually?


There is no obvious use for the extra pair from Farringdon to
Moorgate, sad really.


I think it's to be used at least in part as a stabling location for the new
(longer) S-stock - at the moment part of it is being used as a worksite
(storage etc) for the Farringdon Thameslink works - might also prove useful
(indeed could well be part of the plan) to utilise it in the same capacity
for Crossrail works too.


Will "S" stock be able to reverse at Aldgate? The problem with
utilizing the tracks and/or platforms on the Moorgate widened lines is
that terminating trains have to cross the anti-clockwise Circle line
in a conflicting movement. The same would apply were the terminal
platform at Liverpool Street restored.

Jamie Thompson November 26th 10 12:14 PM

Thameslink programme to go ahead "in it's entirety"
 
On Nov 26, 10:24*am, 1506 wrote:
On Nov 25, 6:03*pm, "Mizter T" wrote:

"1506" wrote:
On Nov 25, 8:27 am, wrote:


Anyone know what the plans are for the remaining parts of the moorgate
line
are? Will LU take them over eventually?


There is no obvious use for the extra pair from Farringdon to
Moorgate, sad really.


I think it's to be used at least in part as a stabling location for the new
(longer) S-stock - at the moment part of it is being used as a worksite
(storage etc) for the Farringdon Thameslink works - might also prove useful
(indeed could well be part of the plan) to utilise it in the same capacity
for Crossrail works too.


Will "S" stock be able to reverse at Aldgate? *The problem with
utilizing the tracks and/or platforms on the Moorgate widened lines is
that terminating trains have to cross the anti-clockwise Circle line
in a conflicting movement. *The same would apply were the terminal
platform at Liverpool Street restored.


....one of the reasons I would've thought that the Crossrail works in
Finsbury Circus would've been a golden opportunity to knock through
the SSL's terminating platforms at Moorgate (or indeed, the former
Thameslink bays) to connect up with the SSL under Finsbury Circus (or
extended to Liverpool St.).

There's the option of just knocking through a single track tunnel from
one of the bays to get central terminating bays to remove the
conflicting moves, or there's the option of knocking through a couple
of the bays to give bidirectional terminating capability. That could
provide a pair of centre terminating roads, accessible from both
sides, and depending on what layout was chosen, there could even be a
pair of directional islands.

[email protected] November 26th 10 12:17 PM

Thameslink programme to go ahead "in it's entirety"
 
In article ,
(Mizter T) wrote:

"Basil Jet" wrote:

On 2010\11\25 18:21, Mizter T wrote:

"Paul Corfield" wrote:

On Thu, 25 Nov 2010 16:27:42 +0000 (UTC),
d
wrote:

Anyone know what the plans are for the remaining parts of the
moorgate line are? Will LU take them over eventually?

I thought something had been said in Modern Railways about the
remaining alignment (net of any incursions by Crossrail or
Thameslink works) was being considered as potential stabling
sidings for LUL use. I might be imagining it though!

I don't think you are, though I don't think I've ever read or heard
anything solid about it. From a layman's point of view it'd seems
like a decent location for some sidings.


Given the value of land in the area, it's a decent location for
pretty much anything but sidings. [...]


I disagree - this is a two-track width railway bed in a cutting
next to an operational two-track railway, and the cutting is
surrounded by buildings already. I'm not trying to suggest that
there couldn't be various clever ways of fitting in some
development into this space, but it's a rather constrained linear
location (/locations) which is hardly ideal for development.

[...] There's a disused bay platform at Liverpool Street behind
shutters, so there can't be much need for extra track in the area..


AIUI the issue w.r.t. the new S-stock trains is that they're going
to be too long for several of the present stabling sidings that
exist on the sub-surface railway. I'm not sure if the bay platform
at Liverpool Street would be workable, and I rather doubt that it
alone would satisfy the apparent need.


They could do both of course. Use the trackbed for new sidings and
construct new buildings above them like over most of that part of the
Metropolitan.

--
Colin Rosenstiel

[email protected] November 26th 10 12:17 PM

Thameslink programme to go ahead "in it's entirety"
 
In article , (Roland
Perry) wrote:

In message , at 19:10:08
on Thu, 25 Nov 2010, Jim Chisholm
remarked:

istr they were supposed to be lengthening platforms at Cambridge to
take 12 cars, but I think they may have changed their mind and are
doing an island instead.


As well, not instead.

Cambridge has had 12-car Class 365 services to Kings Cross in the
morning peak for some time now.

Isn't that being done by some sort of kludge, rather than lengthening
both platforms 1 & 4 so that all trains could be 12-car, as was
originally proposed?


The Island Platform at Cambridge is due to be opened in just over a
year. They've possessions booked, and it is needed for the proposed 12
car service to Liverpool St, trains for which are already being
produced.


If both 1 & 4 were usable by 12-car trains, perhaps they wouldn't
need such a long island. Do you know whether they've changed
strategy, or will 1 & 4 & the island all be capable of 12-car?


Extending 1 and 4 was part of the Thameslink Programme. 1 was extended
early to allow FCC to run a few 12-car trains in the peak (two up trains
at present but that might change in December).

Only extending 1 & 4 would not provide the terminating capacity needed for
West Anglia 12-car trains that start in December next year, however.

Hence the accelerated programme for the island platform. A bit of an oops
from the lack of coordination between GN and WA routes. Once the island is
there I expect the platform 4 extension will not proceed.

--
Colin Rosenstiel

[email protected] November 26th 10 12:17 PM

Thameslink programme to go ahead "in it's entirety"
 
In article , (Roland
Perry) wrote:

In message , at 21:17:40 on
Thu, 25 Nov 2010, Roy Badami remarked:
Isn't that being done by some sort of kludge, rather than lengthening
both platforms 1 & 4 so that all trains could be 12-car, as was
originally proposed?


What kind of kludge? I thought I read here that some work (not sure
what) was done a while back to allow platform 1 to accommodate the
12-car trains.

I don't think the 12-car trains straddle platforms 1 & 4, if that's
what you mean?


Yes, that's what I meant; but I haven't seen any positive
indications either way (other than perhaps a lack of people
commenting how they've seen a 12-car in Platform 1 that didn't foul
the x-over).


Do keep up, Roland! Class 317 12 car trains could already fit in platform
1 but class 365 units are slightly longer so the platform had to be
slightly extended. There were no changes at the crossover end at all.

--
Colin Rosenstiel


All times are GMT. The time now is 10:36 AM.

Powered by vBulletin®
Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Copyright ©2004-2006 LondonBanter.co.uk