|
GOSPEL Electrification
The line between Barking and Gospel Oak is due to be
re-opened at the end of this month. I have assumed all along that the entire electrification project and attendant rebuilding work will be completed by then. Certainly I have not seen statements from TfL or Network Rail warning of further weekend closures after the line is re-opened to allow more work to be done. At present on much of the route the stanchions to support overhead wiring are not yet in place. I don't know how long it takes to install these stanchions or to string up overhead wiring, but it seems quite possible that this work will not be completed within the next 24 days. Does anyone know whether or not the original plan was to complete the project fully by the end of February? |
Stanchions are now being installed but in a piecemeal
way that seems to flout common sense. A complete one was erected at Leyton Midland Station several weeks ago and then left in isolation. A few weeks later a second was installed. That too was not followed up. Now a single upright column has been erected. I admit openly I do not understand this methodology. |
Paris Shows The Way!
Robin9 wrote on 14 Feb 2017 at
16:30 ... British politicians, particularly those in London, love to pretend that they are concerned about traffic congestion and the consequential air pollution. They persist with policies which have been proved not to work, and refuse to listen to people who drive in traffic day after day and have a real understanding of the main cause of the problem. It seems that in Paris someone in authority is less bigoted than our politicians: http://tinyurl.com/jxlb4kc How refreshing! I am deeply envious. Ealing have been doing that for several years, e.g. the traffic lights at the T-junction outside Acton Town station (opposite the entrance to the LT Museum Depot) were replaced by a mini-roundabout and a zebra crossing about 5 years ago. -- Richard J. (to email me, swap 'uk' and 'yon' in address) |
Paris Shows The Way!
On 2017-02-14 23:01:46 +0000, Richard J. said:
Ealing have been doing that for several years, e.g. the traffic lights at the T-junction outside Acton Town station (opposite the entrance to the LT Museum Depot) were replaced by a mini-roundabout and a zebra crossing about 5 years ago. Luton airport for years had a terrible congestion problem on a Monday morning. This started happening soon after a set of traffic lights was installed at the approach roundabout. "Get rid of them" said us regulars. "No" said the airport. And on it went. Eventually they did get rid of them, and the problem went away. The problem with traffic lights, of course, is that they block traffic movement during the "overlap" between two phases - replace with something else e.g. a roundabout and traffic can move all of the time. What you replace it with does require some thought as roundabouts don't cope well with unbalanced flows, but lights on all approaches to a junction basically waste time. If lights are needed to balance flows, not having lights on one branch of the roundabout works quite well - during the "overlap" time, traffic can then flow from that branch. Neil -- Neil Williams Put my first name before the @ to reply. |
Paris Shows The Way!
On Wed, 15 Feb 2017 00:10:31 +0000
Neil Williams wrote: On 2017-02-14 23:01:46 +0000, Richard J. said: Ealing have been doing that for several years, e.g. the traffic lights at the T-junction outside Acton Town station (opposite the entrance to the LT Museum Depot) were replaced by a mini-roundabout and a zebra crossing about 5 years ago. Luton airport for years had a terrible congestion problem on a Monday morning. This started happening soon after a set of traffic lights was installed at the approach roundabout. Putting traffic lights on roundabouts has always struck me as a ridiculous thing to do. Its as if the traffic planners didn't quite understand the purpose of a roundabout or how it worked and assumed it was no different to a 4 way junction. Once you've added the lights the roundabout is now completely redundant and you'd probably get better traffic flow if you did replace it with a simple junction. What you replace it with does require some thought as roundabouts don't cope well with unbalanced flows, but lights on all approaches to a junction basically waste time. If lights are needed to balance flows, not having lights on one branch of the roundabout works quite well - during the "overlap" time, traffic can then flow from that branch. Roundabouts generally work pretty well on their own. Stirling corner on the A1 has intermittent lights. The only time serious queues build up is when they switch the damn things on. -- Spud |
Paris Shows The Way!
|
Paris Shows The Way!
|
Paris Shows The Way!
wrote in message ... On Wed, 15 Feb 2017 00:10:31 +0000 Neil Williams wrote: On 2017-02-14 23:01:46 +0000, Richard J. said: Ealing have been doing that for several years, e.g. the traffic lights at the T-junction outside Acton Town station (opposite the entrance to the LT Museum Depot) were replaced by a mini-roundabout and a zebra crossing about 5 years ago. Luton airport for years had a terrible congestion problem on a Monday morning. This started happening soon after a set of traffic lights was installed at the approach roundabout. Putting traffic lights on roundabouts has always struck me as a ridiculous thing to do. Its as if the traffic planners didn't quite understand the purpose of a roundabout or how it worked and assumed it was no different to a 4 way junction. Once you've added the lights the roundabout is now completely redundant and you'd probably get better traffic flow if you did replace it with a simple junction. bit difficult to do when the roundabout is above a motorway junction tim |
Paris Shows The Way!
On 2017-02-15 10:46:24 +0000, tim... said:
bit difficult to do when the roundabout is above a motorway junction There are plenty of cases where it isn't, e.g. the roundabout in Slough made famous by "The Office" which was indeed removed and replaced with a signalled junction. OTOH, traffic signals on roundabouts often do make sense to solve a specific problem involving unbalanced flows without reducing the capacity of the junction. Neil -- Neil Williams Put my first name before the @ to reply. |
Paris Shows The Way!
On Wed, 15 Feb 2017 10:26:15 +0000
Neil Williams wrote: On 2017-02-15 09:38:59 +0000, d said: Putting traffic lights on roundabouts has always struck me as a ridiculous thing to do. Its as if the traffic planners didn't quite understand the purpose of a roundabout or how it worked and assumed it was no different to a 4 way junction. Once you've added the lights the roundabout is now completely redundant and you'd probably get better traffic flow if you did replace it with a simple junction. Roundabouts work very well where there is a reasonably balanced traffic flow on all 4 (or more) arms. They fail badly where the traffic is highly directional, e.g. towards a city centre. Which is when a normal signalled junction should have been installed. The way to prevent this is to place traffic lights on all but one of the arms, having no lights on an arm that is not a "blocking" flow but does have reasonable demand. In the example above, putting them on all but arm C would allow continuous traffic flow, but would regulate arm B such that those on arm C could get out and queueing is prevented. This has an advantage over a traditional traffic light junction as traffic is always flowing - when the lights are on amber or all on red Or just have junctions with the american system of turn on red and at less busy times simply have flashing orange on all approaches. -- Spud |
Paris Shows The Way!
|
Paris Shows The Way!
On Wed, 15 Feb 2017 10:46:24 -0000
"tim..." wrote: wrote in message ... On Wed, 15 Feb 2017 00:10:31 +0000 Neil Williams wrote: On 2017-02-14 23:01:46 +0000, Richard J. said: Ealing have been doing that for several years, e.g. the traffic lights at the T-junction outside Acton Town station (opposite the entrance to the LT Museum Depot) were replaced by a mini-roundabout and a zebra crossing about 5 years ago. Luton airport for years had a terrible congestion problem on a Monday morning. This started happening soon after a set of traffic lights was installed at the approach roundabout. Putting traffic lights on roundabouts has always struck me as a ridiculous thing to do. Its as if the traffic planners didn't quite understand the purpose of a roundabout or how it worked and assumed it was no different to a 4 way junction. Once you've added the lights the roundabout is now completely redundant and you'd probably get better traffic flow if you did replace it with a simple junction. bit difficult to do when the roundabout is above a motorway junction There will always be exceptions. But having roundabouts as motorway junctions isn't a requirement. In america the offramp almost always leads to a junction and in europe its a toss up whether theres one or not though on the french toll autoroutes there is almost never one at the actual exit. If there is one its usually way past the toll booths. -- Spud |
Paris Shows The Way!
On 15/02/2017 13:50, d wrote:
On Wed, 15 Feb 2017 10:26:15 +0000 Neil Williams wrote: On 2017-02-15 09:38:59 +0000, d said: Putting traffic lights on roundabouts has always struck me as a ridiculous thing to do. Its as if the traffic planners didn't quite understand the purpose of a roundabout or how it worked and assumed it was no different to a 4 way junction. Once you've added the lights the roundabout is now completely redundant and you'd probably get better traffic flow if you did replace it with a simple junction. Roundabouts work very well where there is a reasonably balanced traffic flow on all 4 (or more) arms. They fail badly where the traffic is highly directional, e.g. towards a city centre. Which is when a normal signalled junction should have been installed. The way to prevent this is to place traffic lights on all but one of the arms, having no lights on an arm that is not a "blocking" flow but does have reasonable demand. In the example above, putting them on all but arm C would allow continuous traffic flow, but would regulate arm B such that those on arm C could get out and queueing is prevented. This has an advantage over a traditional traffic light junction as traffic is always flowing - when the lights are on amber or all on red Or just have junctions with the american system of turn on red and at less busy times simply have flashing orange on all approaches. I'd like to see you implement that or any other of your designs at the Redbridge roundabout: ,18z (I would put negotiating it when the lights are out of action in the same class as Sir Thomas Beecham's famous two.) -- Robin reply-to address is (intended to be) valid |
Paris Shows The Way!
|
Paris Shows The Way!
In message , at 12:02:15 on Wed, 15 Feb
2017, Basil Jet remarked: I'm amazed part-time lights at roundabouts are allowed. It seems obvious to me that every time a blown red bulb faces traffic already on the roundabout, you will have traffic joining the roundabout seeing a green light and thinking it has the priority, and the traffic on the roundabout seeing no light and thinking it has the priority. There will usually (always?) be two red lights. And in any event, green doesn't mean "full steam ahead", rather than "proceed with caution". -- Roland Perry |
Paris Shows The Way!
On 2017-02-15 15:02:33 +0000, Roland Perry said:
There will usually (always?) be two red lights. And in any event, green doesn't mean "full steam ahead", rather than "proceed with caution". Yes, with road traffic there is, unlike railway signalling, nothing ever that says it is absolutely safe to proceed. However, I suspect most drivers don't treat it that way. LEDs of course reduce the chance of this, and these days it should be reasonably easily possible to make all the red lights provable and in the absence of them all working turn them all off. Neil -- Neil Williams Put my first name before the @ to reply. |
Paris Shows The Way!
In article , d () wrote:
On Wed, 15 Feb 2017 04:41:39 -0600 wrote: If you made any attempt to understand traffic engineering, there are conditions when roundabouts really don't work. If traffic levels are high and flows unbalanced then some arms can't get out onto the roundabout unless traffic lights are installed. Translation: "Just do what I do - read someone elses post then paraphrase and pretend I knew it all along. Win!" No. I have direct experience acquired over decades of hearing from traffic engineers. It was pure coincidence that someone, probably with similar experience, made similar comments which I only saw after posting mine. -- Colin Rosenstiel |
Paris Shows The Way!
On Wed, 15 Feb 2017 14:09:08 +0000
Robin wrote: I'd like to see you implement that or any other of your designs at the Redbridge roundabout: 58967,0.0434959,18z (I would put negotiating it when the lights are out of action in the same class as Sir Thomas Beecham's famous two.) I've used that junction plenty of times. Tbh I'd say stirling corner and apex corner are a lot worse but its all subjective. -- Spud |
Paris Shows The Way!
wrote in message ... Or just have junctions with the american system of turn on red which is complete useless at traffic light controlled roundabouts as all of the traffic is nominally turning left tim |
Paris Shows The Way!
wrote in message ... On Wed, 15 Feb 2017 10:46:24 -0000 "tim..." wrote: wrote in message ... On Wed, 15 Feb 2017 00:10:31 +0000 Neil Williams wrote: On 2017-02-14 23:01:46 +0000, Richard J. said: Ealing have been doing that for several years, e.g. the traffic lights at the T-junction outside Acton Town station (opposite the entrance to the LT Museum Depot) were replaced by a mini-roundabout and a zebra crossing about 5 years ago. Luton airport for years had a terrible congestion problem on a Monday morning. This started happening soon after a set of traffic lights was installed at the approach roundabout. Putting traffic lights on roundabouts has always struck me as a ridiculous thing to do. Its as if the traffic planners didn't quite understand the purpose of a roundabout or how it worked and assumed it was no different to a 4 way junction. Once you've added the lights the roundabout is now completely redundant and you'd probably get better traffic flow if you did replace it with a simple junction. bit difficult to do when the roundabout is above a motorway junction There will always be exceptions. But having roundabouts as motorway junctions isn't a requirement. well no but we do have them and IME they are invariable the ones where traffic lights have been installed to "improve" flow (admittedly not all of them are of the "above the motorway" variety) tim |
Paris Shows The Way!
On Wed, 15 Feb 2017 09:40:41 -0600
wrote: In article , d () wrote: On Wed, 15 Feb 2017 04:41:39 -0600 wrote: If you made any attempt to understand traffic engineering, there are conditions when roundabouts really don't work. If traffic levels are high and flows unbalanced then some arms can't get out onto the roundabout unless traffic lights are installed. Translation: "Just do what I do - read someone elses post then paraphrase and pretend I knew it all along. Win!" No. I have direct experience acquired over decades of hearing from traffic engineers. It was pure coincidence that someone, probably with similar experience, made similar comments which I only saw after posting mine. Sure, complete coincidence. And no doubt you also aquired extensive experience of air traffic control when you worked for Porcine Airlines. -- Spud |
Paris Shows The Way!
|
Paris Shows The Way!
In article , d () wrote:
On Wed, 15 Feb 2017 09:40:41 -0600 wrote: In article , d () wrote: On Wed, 15 Feb 2017 04:41:39 -0600 wrote: If you made any attempt to understand traffic engineering, there are conditions when roundabouts really don't work. If traffic levels are high and flows unbalanced then some arms can't get out onto the roundabout unless traffic lights are installed. Translation: "Just do what I do - read someone elses post then paraphrase and pretend I knew it all along. Win!" No. I have direct experience acquired over decades of hearing from traffic engineers. It was pure coincidence that someone, probably with similar experience, made similar comments which I only saw after posting mine. Sure, complete coincidence. And no doubt you also aquired extensive experience of air traffic control when you worked for Porcine Airlines. Do you accept information from anyone or just make silly comments all the time? -- Colin Rosenstiel |
Paris Shows The Way!
On Wed, 15 Feb 2017 16:25:14 -0000
"tim..." wrote: wrote in message ... Or just have junctions with the american system of turn on red which is complete useless at traffic light controlled roundabouts as all of the traffic is nominally turning left Do try and keep up. I was talking about if roundabouts were replaced with junctions. -- Spud |
Paris Shows The Way!
On Wed, 15 Feb 2017 19:06:28 -0600
wrote: In article , d () wrote: Sure, complete coincidence. And no doubt you also aquired extensive experience of air traffic control when you worked for Porcine Airlines. Do you accept information from anyone or just make silly comments all the time? When someone has used virtually identical phrases from someone elses post made earlier after having not even broached the subject before and then suddenly claims to have lots of experience in the matter you'll have to excuse me if I take it with a whole salt mine. -- Spud |
Both yesterday and today, and possibly earlier, two-car
DMUs have been travelling along the line, presumably for driver training/route familiarisation purposes. Strolling around Leytonstone this afternoon, I noticed that three bridges in the elevated section in the Samson Road/ Montague Road area have been replaced. |
GOSPEL Electrification
Robin9 wrote:
Both yesterday and today, and possibly earlier, two-car DMUs have been travelling along the line, presumably for driver training/route familiarisation purposes. Presumably the line's own 172s? They've been parked at Willesden during the closure. Strolling around Leytonstone this afternoon, I noticed that three bridges in the elevated section in the Samson Road/ Montague Road area have been replaced. |
GOSPEL Electrification
On Sun, 19 Feb 2017 21:45:36 -0000 (UTC)
Recliner wrote: Robin9 wrote: Both yesterday and today, and possibly earlier, two-car DMUs have been travelling along the line, presumably for driver training/route familiarisation purposes. Presumably the line's own 172s? They've been parked at Willesden during the closure. I'm surprised TfL hasn't sold them given they'll be redundant on the LO network when electrification is complete. -- Spud |
GOSPEL Electrification
|
GOSPEL Electrification
|
GOSPEL Electrification
On Mon, 20 Feb 2017 11:37:08 +0000
Roland Perry wrote: In message , at 11:08:35 on Mon, 20 Feb 2017, d remarked: Both yesterday and today, and possibly earlier, two-car DMUs have been travelling along the line, presumably for driver training/route familiarisation purposes. Presumably the line's own 172s? They've been parked at Willesden during the closure. I'm surprised TfL hasn't sold them I think the lessor (Angel Trains) would have something to say if TfL sold them!! I didn't realised they were leased. Is that a choice TfL made or was it forced upon them I wonder? -- Spud |
GOSPEL Electrification
On Mon, 20 Feb 2017 12:21:54 +0000
Recliner wrote: On Mon, 20 Feb 2017 11:08:35 +0000 (UTC), d wrote: On Sun, 19 Feb 2017 21:45:36 -0000 (UTC) Recliner wrote: Robin9 wrote: Both yesterday and today, and possibly earlier, two-car DMUs have been travelling along the line, presumably for driver training/route familiarisation purposes. Presumably the line's own 172s? They've been parked at Willesden during the closure. I'm surprised TfL hasn't sold them given they'll be redundant on the LO network when electrification is complete. They will be needed when the line reopens this month, partly because the electrification won't be complete, and even after it is, because the new trains don't arrive till next year. There had been local pressure for some other redundant old 4-car EMUs to be used until the new trains arrive, but TfL hasn't shown much enthusiasm. Of course if TfL had ordered a few extra 378s back in 2014.... but we've done that argument. -- Spud |
GOSPEL Electrification
|
GOSPEL Electrification
On Mon, 20 Feb 2017 12:42:03 +0000
Roland Perry wrote: In message , at 12:34:52 on Mon, 20 Feb 2017, d remarked: Both yesterday and today, and possibly earlier, two-car DMUs have been travelling along the line, presumably for driver training/route familiarisation purposes. Presumably the line's own 172s? They've been parked at Willesden during the closure. I'm surprised TfL hasn't sold them I think the lessor (Angel Trains) would have something to say if TfL sold them!! I didn't realised they were leased. Is that a choice TfL made or was it forced upon them I wonder? Almost all rolling stock is leased. And it's TfL imposing it on Arriva Rail London (just as DfT does on its management contracts such as with GTR). AFAIK tube trains are all owned outright by LU. Is this not the case with the 378s on LO then? -- Spud |
GOSPEL Electrification
On Mon, 20 Feb 2017 12:35:57 +0000 (UTC), d wrote:
On Mon, 20 Feb 2017 12:21:54 +0000 Recliner wrote: On Mon, 20 Feb 2017 11:08:35 +0000 (UTC), d wrote: On Sun, 19 Feb 2017 21:45:36 -0000 (UTC) Recliner wrote: Robin9 wrote: Both yesterday and today, and possibly earlier, two-car DMUs have been travelling along the line, presumably for driver training/route familiarisation purposes. Presumably the line's own 172s? They've been parked at Willesden during the closure. I'm surprised TfL hasn't sold them given they'll be redundant on the LO network when electrification is complete. They will be needed when the line reopens this month, partly because the electrification won't be complete, and even after it is, because the new trains don't arrive till next year. There had been local pressure for some other redundant old 4-car EMUs to be used until the new trains arrive, but TfL hasn't shown much enthusiasm. Of course if TfL had ordered a few extra 378s back in 2014.... but we've done that argument. On what basis could TfL have ordered any kind of EMUs in Feb 2013 (when the last 378 carriage order was authorised) for a line whose electrification contract was only awarded in September 2015? You seem to have a remarkably cavalier approach to public spending! You'd be the first to complain if fleets of new trains were ordered prematurely, and then not used because plans had changed. |
GOSPEL Electrification
On Mon, 20 Feb 2017 12:51:49 +0000 (UTC), d wrote:
On Mon, 20 Feb 2017 12:42:03 +0000 Roland Perry wrote: In message , at 12:34:52 on Mon, 20 Feb 2017, d remarked: Both yesterday and today, and possibly earlier, two-car DMUs have been travelling along the line, presumably for driver training/route familiarisation purposes. Presumably the line's own 172s? They've been parked at Willesden during the closure. I'm surprised TfL hasn't sold them I think the lessor (Angel Trains) would have something to say if TfL sold them!! I didn't realised they were leased. Is that a choice TfL made or was it forced upon them I wonder? Almost all rolling stock is leased. And it's TfL imposing it on Arriva Rail London (just as DfT does on its management contracts such as with GTR). AFAIK tube trains are all owned outright by LU. Is this not the case with the 378s on LO then? No |
GOSPEL Electrification
On Mon, 20 Feb 2017 12:53:51 +0000
Recliner wrote: On Mon, 20 Feb 2017 12:35:57 +0000 (UTC), d wrote: Of course if TfL had ordered a few extra 378s back in 2014.... but we've done that argument. On what basis could TfL have ordered any kind of EMUs in Feb 2013 (when the last 378 carriage order was authorised) for a line whose electrification contract was only awarded in September 2015? On the basis that it was likely to happen and a few extra trains couldn't hurt anyway. According to wonkypedia 57 of the 378s were built so another 6 or so (I'm guessing it'll be around that required for the goblin) would hardly have broken the bank considering the overall cost of the whole LO project. Plus there's this interesting snippet: "In July 2015, London Overground announced an order for 45 new Class 710 units, some of which would displace the Class 378s in use on the Watford DC Line. These displaced units will then be cascaded to strengthen services on the other lines the units are used on." So in other words they didn't order enough 378s in the first place. -- Spud |
GOSPEL Electrification
On Mon, 20 Feb 2017 13:15:32 +0000 (UTC), d wrote:
On Mon, 20 Feb 2017 12:53:51 +0000 Recliner wrote: On Mon, 20 Feb 2017 12:35:57 +0000 (UTC), d wrote: Of course if TfL had ordered a few extra 378s back in 2014.... but we've done that argument. On what basis could TfL have ordered any kind of EMUs in Feb 2013 (when the last 378 carriage order was authorised) for a line whose electrification contract was only awarded in September 2015? On the basis that it was likely to happen and a few extra trains couldn't hurt anyway. According to wonkypedia 57 of the 378s were built so another 6 or so (I'm guessing it'll be around that required for the goblin) would hardly have broken the bank considering the overall cost of the whole LO project. Do you think TfL has lots of spare cash sloshing around that it can squander on trains that may never be needed? Do you really know nothing about public sector procurement? Plus there's this interesting snippet: "In July 2015, London Overground announced an order for 45 new Class 710 units, some of which would displace the Class 378s in use on the Watford DC Line. These displaced units will then be cascaded to strengthen services on the other lines the units are used on." So in other words they didn't order enough 378s in the first place. They knew that by 2015. They didn't when the last 378s were ordered, more than two years earlier, or they'd have ordered more. In any case, they'd have still needed to order more trains for the GOBLIN and the new eastern LO lines, and 378 has now been superseded. Better that they get more of the modern train, rather than the old one that costs more to operate. But then, you seem to be keen that TfL wastes as much money as possible, buying more trains that you've previously said you hated. |
GOSPEL Electrification
On Mon, 20 Feb 2017 13:55:11 +0000
Recliner wrote: On Mon, 20 Feb 2017 13:15:32 +0000 (UTC), d wrote: On the basis that it was likely to happen and a few extra trains couldn't hurt anyway. According to wonkypedia 57 of the 378s were built so another 6 or so (I'm guessing it'll be around that required for the goblin) would hardly have broken the bank considering the overall cost of the whole LO project. Do you think TfL has lots of spare cash sloshing around that it can squander on trains that may never be needed? Do you really know nothing about public sector procurement? Clearly they are needed for service improvements elsewhere anyway. Don't tell me they didn't know that before 2015. So in other words they didn't order enough 378s in the first place. They knew that by 2015. They didn't when the last 378s were ordered, more than two years earlier, or they'd have ordered more. In any case, they'd have still needed to order more trains for the GOBLIN and the new eastern LO lines, and 378 has now been superseded. Better that they get more of the modern train, rather than the old one that costs more to operate. But then, you seem to be keen that TfL wastes as much money as possible, buying more trains that you've previously said you hated. So how much cheaper will the 710s be then once you've factored in the extra costs of a new design, driver training, signalling and depot upgrades? Got any independent stats rather than just self serving blurb from Bombardier? Also you seem to have completely missed the point that using seperate EMU types on the goblin keeps the line self contained. If they'd used dual voltage 378s there could have been through services. Thats been shot out the water now unless they're planning on testing and type approving the 710 for the whole NLL. -- Spud |
All times are GMT. The time now is 11:01 AM. |
|
Powered by vBulletin®
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2006 LondonBanter.co.uk