Default Hammersmith Bridge could re-open next summer

https://www.ianvisits.co.uk/blog/202...n-next-summer/


  #2   Report Post  
Old March 19th 21, 10:19 AM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Aug 2003
Posts: 10,125
Default Hammersmith Bridge could re-open next summer

In message , at 09:37:19 on Fri, 19 Mar
2021, D A Stocks remarked:

https://www.ianvisits.co.uk/blog/202...-bridge-could-
re-open-next-summer/


"While the double-decker insert is in place, elements of the
bridge that need repair, including the decking, would be lifted
away using the temporary bridge as a works platform and
transported by barges to an off-site facility for safe repair
and restoration."

Doesn't say if other river traffic would be allowed to resume at the
same time as cars.

See also: https://www.bbc.co.uk/news/uk-england-london-55086118
--
Roland Perry
  #3   Report Post  
Old March 19th 21, 11:38 AM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Jul 2003
Posts: 1,715
Default Hammersmith Bridge could re-open next summer

On 19/03/2021 10:19, Roland Perry wrote:
In message , at 09:37:19 on Fri, 19 Mar
2021, D A Stocks remarked:

https://www.ianvisits.co.uk/blog/202...-bridge-could-
re-open-next-summer/


"While the double-decker insert is in place, elements of the
bridge that need repair, including the decking, would be lifted
away using the temporary bridge as a works platform and
transported by barges to an off-site facility for safe repair
and restoration."

Doesn't say if other river traffic would be allowed to resume at the
same time as cars.

See also: https://www.bbc.co.uk/news/uk-england-london-55086118


Presumably not till the dodgy bits have been removed for restoration.
How much river traffic would there normally be that far upriver?

--
Graeme Wall
This account not read.

  #4   Report Post  
Old March 19th 21, 11:51 AM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Aug 2003
Posts: 10,125
Default Hammersmith Bridge could re-open next summer

In message , at 11:38:43 on Fri, 19 Mar
2021, Graeme Wall remarked:
On 19/03/2021 10:19, Roland Perry wrote:
In message , at 09:37:19 on Fri, 19 Mar
2021, D A Stocks remarked:


https://www.ianvisits.co.uk/blog/202...-bridge-could-
re-open-next-summer/

"While the double-decker insert is in place, elements of
the
bridge that need repair, including the decking, would be lifted
away using the temporary bridge as a works platform and
transported by barges to an off-site facility for safe repair
and restoration."
Doesn't say if other river traffic would be allowed to resume at the
same time as cars.
See also: https://www.bbc.co.uk/news/uk-england-london-55086118


Presumably not till the dodgy bits have been removed for restoration.
How much river traffic would there normally be that far upriver?


A significant number of pleasure craft (some of whom have been stranded
away from their regular moorings), as well as the boat race (and
practising for it).
--
Roland Perry
  #5   Report Post  
Old March 19th 21, 12:28 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Jul 2019
Posts: 895
Default Hammersmith Bridge could re-open next summer

Graeme Wall wrote:
On 19/03/2021 10:19, Roland Perry wrote:
In message , at 09:37:19 on Fri, 19 Mar
2021, D A Stocks remarked:

https://www.ianvisits.co.uk/blog/202...-bridge-could-
re-open-next-summer/


"While the double-decker insert is in place, elements of the
bridge that need repair, including the decking, would be lifted
away using the temporary bridge as a works platform and
transported by barges to an off-site facility for safe repair
and restoration."

Doesn't say if other river traffic would be allowed to resume at the
same time as cars.

See also: https://www.bbc.co.uk/news/uk-england-london-55086118


Presumably not till the dodgy bits have been removed for restoration.
How much river traffic would there normally be that far upriver?


Do we know what the threat to river traffic is? Is it the whole bridge
collapsing into the river, or bits falling off?



  #6   Report Post  
Old March 19th 21, 12:38 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Jul 2003
Posts: 1,715
Default Hammersmith Bridge could re-open next summer

On 19/03/2021 11:51, Roland Perry wrote:
In message , at 11:38:43 on Fri, 19 Mar
2021, Graeme Wall remarked:
On 19/03/2021 10:19, Roland Perry wrote:
In message , at 09:37:19 on Fri, 19 Mar
2021, D A Stocks remarked:


https://www.ianvisits.co.uk/blog/202...-bridge-could-
re-open-next-summer/
Â*Â*Â*Â*Â*Â*Â*Â*Â* "While the double-decker insert is in place, elements of the
Â*Â*Â*Â*Â*Â*Â*Â* bridge that need repair, including the decking, would be lifted
Â*Â*Â*Â*Â*Â*Â*Â* away using the temporary bridge as a works platform and
Â*Â*Â*Â*Â*Â*Â*Â* transported by barges to an off-site facility for safe repair
Â*Â*Â*Â*Â*Â*Â*Â* and restoration."
Â*Doesn't say if other river traffic would be allowed to resume at the
same time as cars.
Â*See also: https://www.bbc.co.uk/news/uk-england-london-55086118


Presumably not till the dodgy bits have been removed for restoration.
How much river traffic would there normally be that far upriver?


A significant number of pleasure craft (some of whom have been stranded
away from their regular moorings), as well as the boat race (and
practising for it).


I was thinking about the various "bin-liner" type movement of rubbish
from the west side of London to the recycling depots to the east. Quite
a lot of that moves by river these days.

See https://upload.wikimedia.org/wikipedia/commons/6/6e/Resource.jpg

--
Graeme Wall
This account not read.



Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Hammersmith Bridge Roland Perry London Transport 15 December 16th 20 02:25 PM
Watford to St Albans tram link could open in 2012 burkey[_2_] London Transport 26 November 8th 10 05:02 PM
7 coats of arms on Hammersmith Bridge Basil Jet London Transport 16 July 19th 09 05:15 PM
Old cars or bikes wtd for Primrose Hill Summer Festival, Saturday 25th June 2005 [email protected] London Transport 1 April 26th 05 03:53 PM
Bus 283 and British Summer Time John Rowland London Transport 5 February 20th 04 08:52 AM


All times are GMT. The time now is 09:02 AM.

Powered by vBulletin®
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 London Banter.
The comments are property of their posters.
 

About Us

"It's about London Transport"

 

Copyright © 2017