On Mar 22, 3:50*pm, Neil Williams wrote:
On Thu, 22 Mar 2012 05:19:58 -0700 (PDT), 77002
wrote:

However, many folks have travelled to the terminus by subway.
Ascending escalators, waiting for a train, and accessing one's
platform all add to the journey time.


True. *But to me fastest is not necessarily best.

Rather wise words Mr. Williams. Thank you.

  #142   Report Post  
Old March 22nd 12, 05:07 PM posted to uk.transport.london,misc.transport.urban-transit,uk.railway
external usenet poster
 
First recorded activity at LondonBanter: Sep 2011
Posts: 267
Default Crossrail tunnelling to start shortly

On Mar 22, 4:00*pm, Neil Williams wrote:
On Thu, 22 Mar 2012 11:10:06 +0000, David Cantrell

wrote:
By "half bathrooms" do you mean "bogs"?


Yes he does. *He has this curious obsession with the use of the US
term in here, largely I think because it winds people up.

There are some depths to which I will not stoop.
  #143   Report Post  
Old March 22nd 12, 08:06 PM posted to uk.transport.london,misc.transport.urban-transit,uk.railway
external usenet poster
 
First recorded activity at LondonBanter: Dec 2008
Posts: 2,008
Default Crossrail tunnelling to start shortly

On Thu, 22 Mar 2012 15:03:36 +0000 (UTC), d
wrote:

On Thu, 22 Mar 2012 14:18:40 +0000
Recliner wrote:
On Thu, 22 Mar 2012 13:46:55 +0000 (UTC),
d
wrote:

On Thu, 22 Mar 2012 05:23:19 -0700 (PDT)
77002 wrote:
By the time Crossrail is built, Paddington to Reading will be
electrified. Crossrail will run to Reading.

Well yes, thats part of the scheme.


Is it? When was that announced?


Unofficially. Maidenhead is hardly the most logical place for a terminus.


So it hasn't been announced, and isn't part of the plan, but is just
your presumption. Given that it's a TfL managed project, and is
ordering sans-toilet trains, Maidenhead may be as far west as it
should go.


Presumably improved now that the Moorgate branch is no more? But


Perhaps, I haven't been on it since that closed. Though given that section
didn't have much traffic

there's still the need to change voltage at Farringdon, something that
won't be needed with XRail.


That takes seconds. The main issue when I used it was the slow speed on the
line itself and the constant stopping.


Maybe also connected with the rebuilding of Blackfriars station?
Certainly, it should be much quicker once the project is complete
(including London Bridge and the new tracks between the two).
  #144   Report Post  
Old March 23rd 12, 08:28 AM posted to uk.transport.london,misc.transport.urban-transit,uk.railway
external usenet poster
 
First recorded activity at LondonBanter: Nov 2009
Posts: 1,920
Default Crossrail tunnelling to start shortly

On Thu, 22 Mar 2012 21:06:09 +0000
Recliner wrote:
Unofficially. Maidenhead is hardly the most logical place for a terminus.


So it hasn't been announced, and isn't part of the plan, but is just
your presumption. Given that it's a TfL managed project, and is
ordering sans-toilet trains, Maidenhead may be as far west as it
should go.


AFAIK the line to reading is "protected". Whatever that means in practice.

That takes seconds. The main issue when I used it was the slow speed on the
line itself and the constant stopping.


Maybe also connected with the rebuilding of Blackfriars station?


They hadn't even started on that when I worked down there. This was 2006-2007.

Certainly, it should be much quicker once the project is complete
(including London Bridge and the new tracks between the two).


Given the money spent one would hope so.

B2003

  #145   Report Post  
Old March 23rd 12, 10:57 AM posted to uk.transport.london,misc.transport.urban-transit,uk.railway
external usenet poster
 
First recorded activity at LondonBanter: Sep 2011
Posts: 267
Default Crossrail tunnelling to start shortly

On Mar 23, 9:28*am, wrote:
On Thu, 22 Mar 2012 21:06:09 +0000

Recliner wrote:
Unofficially. Maidenhead is hardly the most logical place for a terminus.


So it hasn't been announced, and isn't part of the plan, but is just
your presumption. *Given that it's a TfL managed project, and is
ordering sans-toilet trains, Maidenhead may be as far west as it
should go.


AFAIK the line to reading is "protected". Whatever that means in practice..

That takes seconds. The main issue when I used it was the slow speed on the
line itself and the constant stopping.


Maybe also connected with the rebuilding of Blackfriars station?


They hadn't even started on that when I worked down there. This was 2006-2007.

Certainly, it should be much quicker once the project is complete
(including London Bridge and the new tracks between the two).


Given the money spent one would hope so.

The assumption that Crossrail will run to Reading is a reasonable
one. Maidenhead was chosen as the Western Terminus in order to keep
the project within budget. If this remains the case, trains for the
section beyond Maidenhead will share the reliefs from a flat Junction
beyond Paddington to Maidenhead. At Maidenhead Crossrail reversal
will have to be handled within the two relief lines which will coping
with said thru trains.

Meanwhile, the route is being electrified to Reading where ample new
platform accomodation is being constructed. This is happening under a
budget outwith Crossrails.

So, no, the powers that be do not admit that Crossrail will run to
Reading. Received wisdom is that it will.


  #146   Report Post  
Old March 23rd 12, 11:44 AM posted to uk.transport.london,misc.transport.urban-transit,uk.railway
external usenet poster
 
First recorded activity at LondonBanter: Nov 2009
Posts: 1,920
Default Crossrail tunnelling to start shortly

On Fri, 23 Mar 2012 04:57:19 -0700 (PDT)
77002 wrote:
Meanwhile, the route is being electrified to Reading where ample new


Is this going to be the first stage of the electrification of the whole
GWR main line or is that still pie in the sky?

So, no, the powers that be do not admit that Crossrail will run to
Reading. Received wisdom is that it will.


If the infrastructure is already going to be there anyway there's no really
good reason not to.

B2003

  #147   Report Post  
Old March 23rd 12, 02:26 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Oct 2006
Posts: 1,392
Default Crossrail tunnelling to start shortly

On Thu, Mar 22, 2012 at 05:23:19AM -0700, 77002 wrote:
On Mar 22, 11:47=A0am, wrote:
On Thu, 22 Mar 2012 11:10:06 +0000
David Cantrell wrote:
It makes sense to me. =A0An awful lot of journeys will be a hell of a lo=

t
shorter than Maidenhead (not Reading) to Shenfield, and even for those
few people going all the way, it's only an hour and a half, as near as
damnit the same as Richmond to Upminster, which also has no bogs and
no-one seems to mind that.

I suspect the central bit will be packed as people use it as an alternati=

ve
to the tube (assuming Oyster will be valid and they're not going to try i=

t
on with special fares). I don't think you'd want smelly , possibly blocke=

d
toilets in the carraige in that scenario.

Thameslink has on board facilities. Thameslink's central section is
extremely well utilized.


Brighton to Bedford is nearly an hour longer journey, so there's more
reason to have bogs on the trains.

--
David Cantrell | Hero of the Information Age

I apologize if I offended you personally,
I intended to do it professionally.
-- Steve Champeon, on the nanog list
  #149   Report Post  
Old March 23rd 12, 03:38 PM posted to uk.transport.london,misc.transport.urban-transit,uk.railway
external usenet poster
 
First recorded activity at LondonBanter: Sep 2011
Posts: 267
Default Crossrail tunnelling to start shortly

On Mar 23, 12:44*pm, wrote:
On Fri, 23 Mar 2012 04:57:19 -0700 (PDT)

77002 wrote:
Meanwhile, the route is being electrified to Reading where ample new


Is this going to be the first stage of the electrification of the whole
GWR main line or is that still pie in the sky?


This is something about which I have no knowledge. Perhaps someone
will stop by with an answer. AFIK, it is HMG's intention to electrify
the GW mainline. Although curiously work has started on the northern
electrification programs anounced at the same time. I am not aware of
any work on the GW mainline in this regard.

So, no, the powers that be do not admit that Crossrail will run to
Reading. *Received wisdom is that it will.


If the infrastructure is already going to be there anyway there's no really
good reason not to.


Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Crossrail tunnelling complete e27002 aurora London Transport 17 June 9th 15 04:55 PM
Crossrail tunnelling complete e27002 aurora London Transport 23 June 8th 15 09:56 AM
Jubilee line tunnelling this weekend? David Cantrell London Transport 6 April 18th 14 02:54 PM
Crossrail tunnelling pictures Recliner[_2_] London Transport 3 February 28th 13 07:28 PM
Crossrail tunnelling to start shortly 77002 London Transport 1 March 25th 12 09:24 PM


All times are GMT. The time now is 09:11 PM.

Powered by vBulletin®
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 London Banter.
The comments are property of their posters.
 

About Us

"It's about London Transport"

 

Copyright © 2017