|
Goblin electrification
.... the timescale was rumoured to be slipping, according to Modern
Railways, but the contract has now been let. http://www.railtechnologymagazine.co...orewrite=false I had no idea that Barking platform one was not electrified! Won't it become disused when the Barking Reach extension is built? |
Goblin electrification
Basil Jet wrote:
... the timescale was rumoured to be slipping, according to Modern Railways, but the contract has now been let. http://www.railtechnologymagazine.co...orewrite=false I had no idea that Barking platform one was not electrified! Won't it become disused when the Barking Reach extension is built? Always useful to have a diversionary option if there's a problem somewhere! Anna Noyd-Dryver |
Quote:
Leyton I often find this service useful. I didn't see any reference to platforms being lengthened. I assume that will have to wait until patronage has increased. (If they re-opened the route through to St. Pancras, patronage would increase very rapidly!) |
Goblin electrification
Robin9 wrote:
'Basil Jet[_4_ Wrote: ;150369'].... the timescale was rumoured to be slipping, according to Modern Railways, but the contract has now been let. http://tinyurl.com/ns5psws I had no idea that Barking platform one was not electrified! Won't it become disused when the Barking Reach extension is built? I'm very pleased they have brought the costs down. As a resident of Leyton I often find this service useful. I didn't see any reference to platforms being lengthened. I assume that will have to wait until patronage has increased. (If they re-opened the route through to St. Pancras, patronage would increase very rapidly!) Are the platforms already long enough for four-car trains? |
Goblin electrification
In article ,
Recliner wrote: [the goblin] Are the platforms already long enough for four-car trains? No. Most stations that used to have longer platforms have had the length beyond two car closed. This would be easy to fix - repoint the brickwork, repaint all the things, etc. But South Tottenham would be more challenging - extending westwards is tricky becuase there's a bridge over the A10 that way; extending eastwards is tricky becuae there's a junction that way. Google maps will give you a picture - literally. Cheers, Mike -- Mike Bristow |
Goblin electrification
|
Goblin electrification
On 2015\10\01 09:55, Mike Bristow wrote:
In article , Recliner wrote: [the goblin] Are the platforms already long enough for four-car trains? No. Most stations that used to have longer platforms have had the length beyond two car closed. This would be easy to fix - repoint the brickwork, repaint all the things, etc. But South Tottenham would be more challenging - extending westwards is tricky becuase there's a bridge over the A10 that way; extending eastwards is tricky becuae there's a junction that way. Google maps will give you a picture - literally. Google maps suggests that you could easily double the length of the platforms without running into the junction or the A10. |
Quote:
Mitcham Eastfields: platforms that don't line up opposite each other. Eastbound the platform would pass (include) the junction and westbound the platform would have to extend across the High Road on a bridge. Expensive but not difficult. |
Goblin electrification
|
Goblin electrification
|
Goblin electrification
On 2015\10\01 20:33, Steve Fitzgerald wrote:
In message , Paul Corfield writes ... the timescale was rumoured to be slipping, according to Modern Railways, but the contract has now been let. http://www.railtechnologymagazine.co...sons-to-carry- out-electrification-of-gospel-oak-barking-route?dorewrite=false I had no idea that Barking platform one was not electrified! Won't it become disused when the Barking Reach extension is built? In theory yes but I'd want a bolt hole for the trains in case a freight train does something stupid east of Barking or C2C have a rare breakdown. Makes no sense to throw away an important facility and we haven't got the TWA process started never mind signed off for the Barking Riverside extension. New Mayor in May 2016 may have other ideas [1] that could force a change in requirements. [1] e.g. build a tunnel to Thamesmead as part of the initial scope or a very early follow on piece of work. That'd force different requirements at Barking Reach that could affect the scope of the TWAO. Extend the H&C maybe? Under the catenary? |
Goblin electrification
On Wed, 30 Sep 2015 19:55:10 -0500,
wrote: In article , (Paul Corfield) wrote: On Wed, 30 Sep 2015 17:37:21 +0100, Basil Jet wrote: ... the timescale was rumoured to be slipping, according to Modern Railways, but the contract has now been let. http://www.railtechnologymagazine.co...to-carry-out-e lectrification-of-gospel-oak-barking-route?dorewrite=false I had no idea that Barking platform one was not electrified! Won't it become disused when the Barking Reach extension is built? In theory yes but I'd want a bolt hole for the trains in case a freight train does something stupid east of Barking or C2C have a rare breakdown. Makes no sense to throw away an important facility and we haven't got the TWA process started never mind signed off for the Barking Riverside extension. New Mayor in May 2016 may have other ideas [1] that could force a change in requirements. [1] e.g. build a tunnel to Thamesmead as part of the initial scope or a very early follow on piece of work. That'd force different requirements at Barking Reach that could affect the scope of the TWAO. Trouble is that there are two electrification systems at Barking. Platform 1 isn't ideally situated for overhead electrification. What is the problem?. --- This email has been checked for viruses by Avast antivirus software. https://www.avast.com/antivirus |
Goblin electrification
In article ,
(David C) wrote: On Wed, 30 Sep 2015 19:55:10 -0500, wrote: In article , (Paul Corfield) wrote: On Wed, 30 Sep 2015 17:37:21 +0100, Basil Jet wrote: ... the timescale was rumoured to be slipping, according to Modern Railways, but the contract has now been let. http://www.railtechnologymagazine.co...-to-carry-out- electrification-of-gospel-oak-barking-route?dorewrite=false I had no idea that Barking platform one was not electrified! Won't it become disused when the Barking Reach extension is built? In theory yes but I'd want a bolt hole for the trains in case a freight train does something stupid east of Barking or C2C have a rare breakdown. Makes no sense to throw away an important facility and we haven't got the TWA process started never mind signed off for the Barking Riverside extension. New Mayor in May 2016 may have other ideas [1] that could force a change in requirements. [1] e.g. build a tunnel to Thamesmead as part of the initial scope or a very early follow on piece of work. That'd force different requirements at Barking Reach that could affect the scope of the TWAO. Trouble is that there are two electrification systems at Barking. Platform 1 isn't ideally situated for overhead electrification. What is the problem?. Dual electrification is a problem which is why most of the North London Line is no longer third rail electrified. -- Colin Rosenstiel |
Goblin electrification
On Thu, 01 Oct 2015 16:31:08 -0500,
wrote: In article , (David C) wrote: On Wed, 30 Sep 2015 19:55:10 -0500, wrote: In article , (Paul Corfield) wrote: On Wed, 30 Sep 2015 17:37:21 +0100, Basil Jet wrote: ... the timescale was rumoured to be slipping, according to Modern Railways, but the contract has now been let. http://www.railtechnologymagazine.co...-to-carry-out- electrification-of-gospel-oak-barking-route?dorewrite=false I had no idea that Barking platform one was not electrified! Won't it become disused when the Barking Reach extension is built? In theory yes but I'd want a bolt hole for the trains in case a freight train does something stupid east of Barking or C2C have a rare breakdown. Makes no sense to throw away an important facility and we haven't got the TWA process started never mind signed off for the Barking Riverside extension. New Mayor in May 2016 may have other ideas [1] that could force a change in requirements. [1] e.g. build a tunnel to Thamesmead as part of the initial scope or a very early follow on piece of work. That'd force different requirements at Barking Reach that could affect the scope of the TWAO. Trouble is that there are two electrification systems at Barking. Platform 1 isn't ideally situated for overhead electrification. What is the problem?. Dual electrification is a problem which is why most of the North London Line is no longer third rail electrified. Which makes interlining with Underground and South of the Thames route Awkward. |
Goblin electrification
In article ,
(Paul Corfield) wrote: On Wed, 30 Sep 2015 19:55:10 -0500, wrote: Trouble is that there are two electrification systems at Barking. Platform 1 isn't ideally situated for overhead electrification. What? You can see on Google satellite view that the tracks into Platform 1 are not electrified. Given that overhead electrification sits perfectly well beside 4th rail LU electrified tracks at Barking I don't see what the problem is in stringing wires into that platform as part of GOBLIN electrification. Please feel free to tell me what I've missed. I'm not saying it can't be done but it is a lot more complicated to signal so tends to be avoided. The LUL 3rd & 4th rail electrified tracks lie between platform 1 and the overhead electrified tracks, don't they? So the Barking Riverside route won't go near platform 1 so why keep it in service? -- Colin Rosenstiel |
Goblin electrification
On Fri, 02 Oct 2015 06:26:29 -0500,
wrote: In article , (Paul Corfield) wrote: On Wed, 30 Sep 2015 19:55:10 -0500, wrote: Trouble is that there are two electrification systems at Barking. Platform 1 isn't ideally situated for overhead electrification. What? You can see on Google satellite view that the tracks into Platform 1 are not electrified. Given that overhead electrification sits perfectly well beside 4th rail LU electrified tracks at Barking I don't see what the problem is in stringing wires into that platform as part of GOBLIN electrification. Please feel free to tell me what I've missed. I'm not saying it can't be done but it is a lot more complicated to signal so tends to be avoided. The LUL 3rd & 4th rail electrified tracks lie between platform 1 and the overhead electrified tracks, don't they? So the Barking Riverside route won't go near platform 1 so why keep it in service? Sorry but you are not making any sense. As has been mentioned, 25 kV AC electrification has co-existed with the under-ground since 1962without any problems. (Back in the past, LT& BR shared tracks between Bromley by Bow, but that is no longer the case, there is no physical connection between the two systems.) Wiring platform 1 "might" have clearance problems, but single trolley wire OHE is all that is needed there, & the only signal that would require immunisation is the platform starter. The up / down cross-over is already wired, so this should be a cheap (!) & simple project. As for why, Mr. Corfield has already pointed out that a wired turnback with a platform face just might be useful, & maybe it might not be possible to path the whole Goblin service to Barking Riverside through the the platform 7 & 8 bottl-neck at Barking Station. HTH, David C. --- This email has been checked for viruses by Avast antivirus software. https://www.avast.com/antivirus |
Goblin electrification
On Fri, 02 Oct 2015 08:39:06 +0100, e27002 aurora
wrote: On Thu, 01 Oct 2015 16:31:08 -0500, wrote: In article , (David C) wrote: On Wed, 30 Sep 2015 19:55:10 -0500, wrote: In article , (Paul Corfield) wrote: On Wed, 30 Sep 2015 17:37:21 +0100, Basil Jet wrote: ... the timescale was rumoured to be slipping, according to Modern Railways, but the contract has now been let. http://www.railtechnologymagazine.co...-to-carry-out- electrification-of-gospel-oak-barking-route?dorewrite=false I had no idea that Barking platform one was not electrified! Won't it become disused when the Barking Reach extension is built? In theory yes but I'd want a bolt hole for the trains in case a freight train does something stupid east of Barking or C2C have a rare breakdown. Makes no sense to throw away an important facility and we haven't got the TWA process started never mind signed off for the Barking Riverside extension. New Mayor in May 2016 may have other ideas [1] that could force a change in requirements. [1] e.g. build a tunnel to Thamesmead as part of the initial scope or a very early follow on piece of work. That'd force different requirements at Barking Reach that could affect the scope of the TWAO. Trouble is that there are two electrification systems at Barking. Platform 1 isn't ideally situated for overhead electrification. What is the problem?. Dual electrification is a problem which is why most of the North London Line is no longer third rail electrified. Chicken and egg ? If you're putting up OHLE for electric-hauled freight, the trains are AC/DC and the substations are getting long in the tooth (and don't like 313s anyway) then dumping DC altogether seems to be a sensible option. Which makes interlining with Underground and South of the Thames route Awkward. The bits shared with LU remain DC-only and had to cope with differing supplies before AC arrived. 377s, 378s etc. deal with the problem of routes having more than one electrification method. |
Goblin electrification
In message , David C
wrote: I'm not saying it can't be done but it is a lot more complicated to signal so tends to be avoided. The LUL 3rd & 4th rail electrified tracks lie between platform 1 and the overhead electrified tracks, don't they? So the Barking Riverside route won't go near platform 1 so why keep it in service? Sorry but you are not making any sense. As has been mentioned, 25 kV AC electrification has co-existed with the under-ground since 1962without any problems. I think there's a misunderstanding here. There are serious problems with having third (or third/fourth) rail on the same line as 25 kV, to do with earthing and track circuits. Therefore there's good reasons to avoid that. But, on the other hand, I don't believe there's any significant reason not to have 25 kV and third rail on adjacent tracks. Particular with platforms in between. -- Clive D.W. Feather | Home: Mobile: +44 7973 377646 | Web: http://www.davros.org Please reply to the Reply-To address, which is: |
Goblin electrification
Clive D. W. Feather wrote:
In message , David C wrote: I'm not saying it can't be done but it is a lot more complicated to signal so tends to be avoided. The LUL 3rd & 4th rail electrified tracks lie between platform 1 and the overhead electrified tracks, don't they? So the Barking Riverside route won't go near platform 1 so why keep it in service? Sorry but you are not making any sense. As has been mentioned, 25 kV AC electrification has co-existed with the under-ground since 1962without any problems. I think there's a misunderstanding here. There are serious problems with having third (or third/fourth) rail on the same line as 25 kV, to do with earthing and track circuits. Therefore there's good reasons to avoid that. But, on the other hand, I don't believe there's any significant reason not to have 25 kV and third rail on adjacent tracks. Particular with platforms in between. I seem to recall that the reason the AC/DC changeover on the West London Line isn't at Shepherds Bush station is because of possible interference with the H&C line (and that isn't even adjacent). Peter Smyth |
Goblin electrification
In article ,
(David C) wrote: On Fri, 02 Oct 2015 06:26:29 -0500, wrote: In article , (Paul Corfield) wrote: On Wed, 30 Sep 2015 19:55:10 -0500, wrote: Trouble is that there are two electrification systems at Barking. Platform 1 isn't ideally situated for overhead electrification. What? You can see on Google satellite view that the tracks into Platform 1 are not electrified. Given that overhead electrification sits perfectly well beside 4th rail LU electrified tracks at Barking I don't see what the problem is in stringing wires into that platform as part of GOBLIN electrification. Please feel free to tell me what I've missed. I'm not saying it can't be done but it is a lot more complicated to signal so tends to be avoided. The LUL 3rd & 4th rail electrified tracks lie between platform 1 and the overhead electrified tracks, don't they? So the Barking Riverside route won't go near platform 1 so why keep it in service? Sorry but you are not making any sense. As has been mentioned, 25 kV AC electrification has co-existed with the under-ground since 1962without any problems. Not on the same tracks. And 1960s signalling technology wasn't based on electronics. That is more picky. As I said, why was most of the North London converted to 25KV? (Back in the past, LT& BR shared tracks between Bromley by Bow, but that is no longer the case, there is no physical connection between the two systems.) Wiring platform 1 "might" have clearance problems, but single trolley wire OHE is all that is needed there, & the only signal that would require immunisation is the platform starter. The up / down cross-over is already wired, so this should be a cheap (!) & simple project. As for why, Mr. Corfield has already pointed out that a wired turnback with a platform face just might be useful, & maybe it might not be possible to path the whole Goblin service to Barking Riverside through the the platform 7 & 8 bottl-neck at Barking Station. I suppose it might be possible but the immunisation work might make it poor value for money. That was my point. -- Colin Rosenstiel |
Goblin electrification
In article ,
(Paul Corfield) wrote: On Fri, 02 Oct 2015 15:59:30 +0100, David C wrote: On Fri, 02 Oct 2015 06:26:29 -0500, wrote: In article , (Paul Corfield) wrote: On Wed, 30 Sep 2015 19:55:10 -0500, wrote: Trouble is that there are two electrification systems at Barking. Platform 1 isn't ideally situated for overhead electrification. What? You can see on Google satellite view that the tracks into Platform 1 are not electrified. Given that overhead electrification sits perfectly well beside 4th rail LU electrified tracks at Barking I don't see what the problem is in stringing wires into that platform as part of GOBLIN electrification. Please feel free to tell me what I've missed. I'm not saying it can't be done but it is a lot more complicated to signal so tends to be avoided. The LUL 3rd & 4th rail electrified tracks lie between platform 1 and the overhead electrified tracks, don't they? So the Barking Riverside route won't go near platform 1 so why keep it in service? Sorry but you are not making any sense. As has been mentioned, 25 kV AC electrification has co-existed with the under-ground since 1962without any problems. (Back in the past, LT& BR shared tracks between Bromley by Bow, but that is no longer the case, there is no physical connection between the two systems.) Wiring platform 1 "might" have clearance problems, but single trolley wire OHE is all that is needed there, & the only signal that would require immunisation is the platform starter. The up / down cross-over is already wired, so this should be a cheap (!) & simple project. As for why, Mr. Corfield has already pointed out that a wired turnback with a platform face just might be useful, & maybe it might not be possible to path the whole Goblin service to Barking Riverside through the the platform 7 & 8 bottl-neck at Barking Station. And more fundamentally the GOBLIN route will be electrified and equipped with EMUs before the Riverside extension is built (assuming the powers are granted). Therefore you really do need platform 1 to be wired as I doubt you could have GOBLIN trains standing at P7/8 for up to 48 mins an hour when freight and C2C trains have to use the tracks too. Now that is a very fair point. -- Colin Rosenstiel |
Goblin electrification
On 02.10.15 20:01, Paul Corfield wrote:
On Fri, 02 Oct 2015 15:59:30 +0100, David C wrote: On Fri, 02 Oct 2015 06:26:29 -0500, wrote: In article , (Paul Corfield) wrote: On Wed, 30 Sep 2015 19:55:10 -0500, wrote: Trouble is that there are two electrification systems at Barking. Platform 1 isn't ideally situated for overhead electrification. What? You can see on Google satellite view that the tracks into Platform 1 are not electrified. Given that overhead electrification sits perfectly well beside 4th rail LU electrified tracks at Barking I don't see what the problem is in stringing wires into that platform as part of GOBLIN electrification. Please feel free to tell me what I've missed. I'm not saying it can't be done but it is a lot more complicated to signal so tends to be avoided. The LUL 3rd & 4th rail electrified tracks lie between platform 1 and the overhead electrified tracks, don't they? So the Barking Riverside route won't go near platform 1 so why keep it in service? Sorry but you are not making any sense. As has been mentioned, 25 kV AC electrification has co-existed with the under-ground since 1962without any problems. (Back in the past, LT& BR shared tracks between Bromley by Bow, but that is no longer the case, there is no physical connection between the two systems.) Wiring platform 1 "might" have clearance problems, but single trolley wire OHE is all that is needed there, & the only signal that would require immunisation is the platform starter. The up / down cross-over is already wired, so this should be a cheap (!) & simple project. As for why, Mr. Corfield has already pointed out that a wired turnback with a platform face just might be useful, & maybe it might not be possible to path the whole Goblin service to Barking Riverside through the the platform 7 & 8 bottl-neck at Barking Station. And more fundamentally the GOBLIN route will be electrified and equipped with EMUs before the Riverside extension is built (assuming the powers are granted). Therefore you really do need platform 1 to be wired as I doubt you could have GOBLIN trains standing at P7/8 for up to 48 mins an hour when freight and C2C trains have to use the tracks too. When or why do C2C trains go through there? Is it for ECM? |
Goblin electrification
|
Goblin electrification
On Fri, 2 Oct 2015 20:44:43 +0100
"Clive D. W. Feather" wrote: In message , David C wrote: I'm not saying it can't be done but it is a lot more complicated to signal so tends to be avoided. The LUL 3rd & 4th rail electrified tracks lie between platform 1 and the overhead electrified tracks, don't they? So the Barking Riverside route won't go near platform 1 so why keep it in service? Sorry but you are not making any sense. As has been mentioned, 25 kV AC electrification has co-existed with the under-ground since 1962without any problems. I think there's a misunderstanding here. There are serious problems with having third (or third/fourth) rail on the same line as 25 kV, to do with earthing and track circuits. Therefore there's good reasons to avoid that. But, on the other hand, I don't believe there's any significant reason not to have 25 kV and third rail on adjacent tracks. Particular with platforms in between. On a related topic - why was 3rd rail used for the ELLX from Highbury given how new DC lines are actively discouraged? They could have used wires all the way down to past Surrey Quays then switched to 3rd rail like Thameslink. Was it limited clearance in the thames tunnels or just for simplicity - ie cheaper? -- Spud |
Goblin electrification
On Fri, 02 Oct 2015 06:26:29 -0500, rosenstiel wrote:
I'm not saying it can't be done but it is a lot more complicated to signal so tends to be avoided. The LUL 3rd & 4th rail electrified tracks lie between platform 1 and the overhead electrified tracks, don't they? So the Barking Riverside route won't go near platform 1 so why keep it in service? As far as I can tell, P1 at Barking connects to the 'down'[1] GOBLIN just East of the River Roding crossing, with a crossover between the River Roding crossing and the North Circular giving access to the 'up'[1] GOBLIN, the OLE lines then cross the LUL lines on a grade seperated crossing (ie flyover). The OLE doesn't run along the section from the GOBLIN connection to the station. Complicated by the fact that the H&C turns back in 3, and that the through District LUL lines are in 2 (westbound) and 6 (eastbound). The eastbound District line tunnels under the AC lines on the East side of the station. There also seems to be a crossover from westbound District to the GOBLIN, but that doesn't appear to have OLE or DC power. It does appear that running OLE along the extra 900 or so metres between Barking P1 and the River Roding would provide a useful facility at Barking, and it shouldn't impact on the LUL DC lines at all, apart from (possibly) the need to fit an insulated joint between the LUL DC line P2 and the OLE P1 points just northwest of the platforms (or even lift the connection, but I imagine it has a use for delivering stock to the Barking LUL depot). [1] Assuming Baking to be the country end and Gospel Oak the town end. -- Denis McMahon, |
Goblin electrification
On 03.10.15 20:39, Peter Smyth wrote:
wrote: And more fundamentally the GOBLIN route will be electrified and equipped with EMUs before the Riverside extension is built (assuming the powers are granted). Therefore you really do need platform 1 to be wired as I doubt you could have GOBLIN trains standing at P7/8 for up to 48 mins an hour when freight and C2C trains have to use the tracks too. When or why do C2C trains go through there? Is it for ECM? Platforms 7+8 are the normal platforms for all c2c trains towards Dagenham Dock. Peter Smyth My mistake, I thought that you were referring to Gospel Oak. |
Goblin electrification
On Friday, 2 October 2015 21:55:43 UTC+2, Clive D. W. Feather wrote:
In message , David C wrote: I'm not saying it can't be done but it is a lot more complicated to signal so tends to be avoided. The LUL 3rd & 4th rail electrified tracks lie between platform 1 and the overhead electrified tracks, don't they? So the Barking Riverside route won't go near platform 1 so why keep it in service? Sorry but you are not making any sense. As has been mentioned, 25 kV AC electrification has co-existed with the under-ground since 1962without any problems. I think there's a misunderstanding here. There are serious problems with having third (or third/fourth) rail on the same line as 25 kV, to do with earthing and track circuits. Therefore there's good reasons to avoid that. But, on the other hand, I don't believe there's any significant reason not to have 25 kV and third rail on adjacent tracks. Particular with platforms in between. When this topic has been discussed in some detail in the past, the issue with dual electrification of 25 kV overhead and 3rd rail is related to the mutually exclusive requirements for how the running lines are bonded to earth for the return current. My understanding of the signalling related complications (not impossible to overcome if for example axle counters are used) relate to the need to cope with both DC and 50 Hz AC return current in the tracks (and related harmonics) in company with track circuits. All of these concerns, however, seem to relate to the presence of the track return current. In the case of LU style 4th rail, the DC return current is not via the running lines, the 4th rail is electrically isolated. What, therefore, is the issue with 25 kV AC and LU 4th rail combined electrification? Robin |
Goblin electrification
On Fri, 02 Oct 2015 17:30:29 -0500,
wrote: In article , (David C) wrote: On Fri, 02 Oct 2015 06:26:29 -0500, wrote: In article , (Paul Corfield) wrote: On Wed, 30 Sep 2015 19:55:10 -0500, wrote: Trouble is that there are two electrification systems at Barking. Platform 1 isn't ideally situated for overhead electrification. What? You can see on Google satellite view that the tracks into Platform 1 are not electrified. Given that overhead electrification sits perfectly well beside 4th rail LU electrified tracks at Barking I don't see what the problem is in stringing wires into that platform as part of GOBLIN electrification. Please feel free to tell me what I've missed. I'm not saying it can't be done but it is a lot more complicated to signal so tends to be avoided. The LUL 3rd & 4th rail electrified tracks lie between platform 1 and the overhead electrified tracks, don't they? So the Barking Riverside route won't go near platform 1 so why keep it in service? Sorry but you are not making any sense. As has been mentioned, 25 kV AC electrification has co-existed with the under-ground since 1962without any problems. Not on the same tracks. And 1960s signalling technology wasn't based on electronics. That is more picky. As I said, why was most of the North London converted to 25KV? The LT&S was resignalled to modern standards in 1996, & the North London was converted to AC to allow elctirc freight trains tp operate between the G.E. & West coast Mainline (Back in the past, LT& BR shared tracks between Bromley by Bow, but that is no longer the case, there is no physical connection between the two systems.) Wiring platform 1 "might" have clearance problems, but single trolley wire OHE is all that is needed there, & the only signal that would require immunisation is the platform starter. The up / down cross-over is already wired, so this should be a cheap (!) & simple project. As for why, Mr. Corfield has already pointed out that a wired turnback with a platform face just might be useful, & maybe it might not be possible to path the whole Goblin service to Barking Riverside through the the platform 7 & 8 bottl-neck at Barking Station. I suppose it might be possible but the immunisation work might make it poor value for money. That was my point. --- This email has been checked for viruses by Avast antivirus software. https://www.avast.com/antivirus |
Goblin electrification
On Fri, 02 Oct 2015 17:30:29 -0500,
wrote: In article , (David C) wrote: On Fri, 02 Oct 2015 06:26:29 -0500, wrote: In article , (Paul Corfield) wrote: On Wed, 30 Sep 2015 19:55:10 -0500, wrote: Trouble is that there are two electrification systems at Barking. Platform 1 isn't ideally situated for overhead electrification. What? You can see on Google satellite view that the tracks into Platform 1 are not electrified. Given that overhead electrification sits perfectly well beside 4th rail LU electrified tracks at Barking I don't see what the problem is in stringing wires into that platform as part of GOBLIN electrification. Please feel free to tell me what I've missed. I'm not saying it can't be done but it is a lot more complicated to signal so tends to be avoided. The LUL 3rd & 4th rail electrified tracks lie between platform 1 and the overhead electrified tracks, don't they? So the Barking Riverside route won't go near platform 1 so why keep it in service? Sorry but you are not making any sense. As has been mentioned, 25 kV AC electrification has co-existed with the under-ground since 1962without any problems. Not on the same tracks. And 1960s signalling technology wasn't based on electronics. That is more picky. As I said, why was most of the North London converted to 25KV? To allow access for Eurostars to reach the GN, & electric freights to run from the GE to the West Coast ML? As for the old LTS signalling, it was replaced in 1996 when Upminster IECC went operational. (Back in the past, LT& BR shared tracks between Bromley by Bow, but that is no longer the case, there is no physical connection between the two systems.) Wiring platform 1 "might" have clearance problems, but single trolley wire OHE is all that is needed there, & the only signal that would require immunisation is the platform starter. The up / down cross-over is already wired, so this should be a cheap (!) & simple project. As for why, Mr. Corfield has already pointed out that a wired turnback with a platform face just might be useful, & maybe it might not be possible to path the whole Goblin service to Barking Riverside through the the platform 7 & 8 bottl-neck at Barking Station. I suppose it might be possible but the immunisation work might make it poor value for money. That was my point. What immunisation work? One signal might need work, but the two systems seem to co-exist side by side without any obvious problems, even at Upminster where the LUL tracks are flanked by two separate 25kV installations! (The LTS mainline & the Upminster - Romford branch.) As for value for money, does the Goblin scheme include any of the possible junctions with existing 25kV routes, such as to the GN at Harringay, or the Midland / Thameslink connection from Junction Road Junction? --- This email has been checked for viruses by Avast antivirus software. https://www.avast.com/antivirus |
Goblin electrification
On 2015\10\17 13:52, David C wrote:
As for value for money, does the Goblin scheme include any of the possible junctions with existing 25kV routes, such as to the GN at Harringay, or the Midland / Thameslink connection from Junction Road Junction? Yes and yes, as mentioned in the webpage listed in the OP. "The CP5 enhancements delivery plan published in June detailed the core electrification scheme in the line: Gospel Oak Junction to South Tottenham West Junction; Gospel Oak platform 3 (bay platform); Carlton Road Junction to Junction Road Junction; Upper Holloway Reception Line; Harringay Park Junction to Harringay Junction; South Tottenham East Junction to Woodgrange Park Junction; Barking Station Junction to Barking Platform 1 buffer stops; and All crossovers between Gospel Oak Junction / Carlton Road Junction and Barking Station Junction" |
Goblin electrification
On 17/10/2015 15:38, Paul Corfield wrote:
That's a wee bit earlier than I expected but is a clear sign that the dreaded "pause" word doesn't seem to affect GOBLIN electrification. I thought the bits that had been paused had now been unpaused anyway? |
Goblin electrification
|
Goblin electrification
Someone Somewhere wrote:
On 17/10/2015 15:38, Paul Corfield wrote: That's a wee bit earlier than I expected but is a clear sign that the dreaded "pause" word doesn't seem to affect GOBLIN electrification. I thought the bits that had been paused had now been unpaused anyway? Unpaused, but delayed. |
Goblin electrification
On 18/10/2015 16:30, Recliner wrote:
Someone Somewhere wrote: On 17/10/2015 15:38, Paul Corfield wrote: That's a wee bit earlier than I expected but is a clear sign that the dreaded "pause" word doesn't seem to affect GOBLIN electrification. I thought the bits that had been paused had now been unpaused anyway? Unpaused, but delayed. Yes - but originally there were fears they were to be cancelled |
Goblin electrification
Someone Somewhere wrote:
On 18/10/2015 16:30, Recliner wrote: Someone Somewhere wrote: On 17/10/2015 15:38, Paul Corfield wrote: That's a wee bit earlier than I expected but is a clear sign that the dreaded "pause" word doesn't seem to affect GOBLIN electrification. I thought the bits that had been paused had now been unpaused anyway? Unpaused, but delayed. Yes - but originally there were fears they were to be cancelled I think that was always scare-mongering by people with a political agenda. |
Goblin electrification
On 18.10.15 16:58, Recliner wrote:
Someone Somewhere wrote: On 18/10/2015 16:30, Recliner wrote: Someone Somewhere wrote: On 17/10/2015 15:38, Paul Corfield wrote: That's a wee bit earlier than I expected but is a clear sign that the dreaded "pause" word doesn't seem to affect GOBLIN electrification. I thought the bits that had been paused had now been unpaused anyway? Unpaused, but delayed. Yes - but originally there were fears they were to be cancelled I think that was always scare-mongering by people with a political agenda. I imagine that this was under discussion before, but do they plan to run 5-car trains as on the ELL/NLL? |
Goblin electrification
|
Goblin electrification
On 18.10.15 18:04, Recliner wrote:
wrote: On 18.10.15 16:58, Recliner wrote: Someone Somewhere wrote: On 18/10/2015 16:30, Recliner wrote: Someone Somewhere wrote: On 17/10/2015 15:38, Paul Corfield wrote: That's a wee bit earlier than I expected but is a clear sign that the dreaded "pause" word doesn't seem to affect GOBLIN electrification. I thought the bits that had been paused had now been unpaused anyway? Unpaused, but delayed. Yes - but originally there were fears they were to be cancelled I think that was always scare-mongering by people with a political agenda. I imagine that this was under discussion before, but do they plan to run 5-car trains as on the ELL/NLL? No, already discussed here recently. It will have 4-car Aventras, hopefully from 2018. It's not certain if some platform extensions will be needed even for those, but probably. I see. And when do they plan to start turning wheels in anger under the wires? |
Goblin electrification
wrote:
On 18.10.15 18:04, Recliner wrote: wrote: On 18.10.15 16:58, Recliner wrote: Someone Somewhere wrote: On 18/10/2015 16:30, Recliner wrote: Someone Somewhere wrote: On 17/10/2015 15:38, Paul Corfield wrote: That's a wee bit earlier than I expected but is a clear sign that the dreaded "pause" word doesn't seem to affect GOBLIN electrification. I thought the bits that had been paused had now been unpaused anyway? Unpaused, but delayed. Yes - but originally there were fears they were to be cancelled I think that was always scare-mongering by people with a political agenda. I imagine that this was under discussion before, but do they plan to run 5-car trains as on the ELL/NLL? No, already discussed here recently. It will have 4-car Aventras, hopefully from 2018. It's not certain if some platform extensions will be needed even for those, but probably. I see. And when do they plan to start turning wheels in anger under the wires? As I said, 2018. |
All times are GMT. The time now is 01:37 PM. |
|
Powered by vBulletin®
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2006 LondonBanter.co.uk