Stratford DLR
I see there are replacement buses running from Bow Church to Stratford this
weekend, is this a sign of progress on the new platforms, or just normal maintenance? The first new platform was supposed to open in January this year... Paul S |
#2
|
|||
|
|||
Stratford DLR
In ,
Paul Scott typed: I see there are replacement buses running from Bow Church to Stratford this weekend, is this a sign of progress on the new platforms, or just normal maintenance? The first new platform was supposed to open in January this year... http://www.tfl.gov.uk/dlr/service_in...1_100307.shtml Buses replace trains between Stratford and Bow Church Due to engineering works for the construction of a new DLR station at Stratford. From 10/03/2007 until 11/03/2007 The replacement bus service will operate to Stratford, Pudding Mill Lane and Bow Church stations, at a 10 minute frequency. A ticket valid on DLR is required before boarding the bus. Mobility impaired passengers who cannot use the replacement bus service are advised to call 020 7363 9700 for further advice. All other routes will be operating during this closure. For further information pick up a leaflet or call DLR Customer Services on 020 7363 9700. For advice on alternative routes during this disruption call 020 7222 1234 or use Journey Planner. Passengers travelling on the affected route are advised to allow extra time for their journey. We apologise for any inconvenience. -- Bob |
#3
|
|||
|
|||
Stratford DLR
"Bob Wood" wrote in message ... I see there are replacement buses running from Bow Church to Stratford this weekend, is this a sign of progress on the new platforms, or just normal maintenance? The first new platform was supposed to open in January this year... http://www.tfl.gov.uk/dlr/service_in...1_100307.shtml That's what I saw earlier - just wondering what the actual work involved was ging to involve - not 'normal maintenance' obviously... Paul |
#4
|
|||
|
|||
Stratford DLR
On Mar 5, 3:52 pm, "Paul Scott"
wrote: "Bob Wood" wrote in message ... I see there are replacement buses running from Bow Church to Stratford this weekend, is this a sign of progress on the new platforms, or just normal maintenance? The first new platform was supposed to open in January this year... http://www.tfl.gov.uk/dlr/service_in...1_100307.shtml That's what I saw earlier - just wondering what the actual work involved was ging to involve - not 'normal maintenance' obviously... Paul This is the second closure of this kind that I am aware of. The other was (I think) some time before Christmas. On that occasion I could see they had carried out works on the ground and on the existing track, presumably to get the alignment and levels right, at the place where the tracks to the new platforms will deviate from the current route. |
#5
|
|||
|
|||
Stratford DLR
On Mar 5, 4:24 pm, "Paul Scott"
wrote: I see there are replacement buses running from Bow Church to Stratford this weekend, is this a sign of progress on the new platforms, or just normal maintenance? The first new platform was supposed to open in January this year... Paul S The updated TfL website now says (hidden away in the DLR 'about' section) the first of the new platforms is due to open in April 2007. Track is now in place on both new platform roads but not yet connected to the main line. It looks like there is still a lot of work to do on the canopies etc but another DLR closure is scheduled over Easter. |
#6
|
|||
|
|||
Stratford DLR
The updated TfL website now says (hidden away in the DLR 'about' section) the first of the new platforms is due to open in April 2007. Track is now in place on both new platform roads but not yet connected to the main line. It looks like there is still a lot of work to do on the canopies etc but another DLR closure is scheduled over Easter. I think the canopies are mostly ready - the real work now is in competition of the rail track and connection to the station. There was footbridge to the Central line platform planned, but since it wasn't even started so far, I think they dropped it from the project :-( |
#7
|
|||
|
|||
Stratford DLR
On Mar 30, 6:19 pm, "alex_t" wrote:
I think the canopies are mostly ready - the real work now is in competition of the rail track and connection to the station. There was footbridge to the Central line platform planned, but since it wasn't even started so far, I think they dropped it from the project :-( And replaced it with a level connection to the new westbound Central Line platform currently under discussion as part of the partial reconstruction of Stratford Regional to cater for the Stratford International branch of the DLR and the new NLL platforms north of the GEML. |
#8
|
|||
|
|||
Stratford DLR
And replaced it with a level connection to the new westbound Central Line platform currently under discussion as part of the partial reconstruction of Stratford Regional to cater for the Stratford International branch of the DLR and the new NLL platforms north of the GEML. Great! So now instead of same platform interchange with Central line (as currently) or dedicated footbridge (as was planned) there will be inconvenient two stairs interchange through existing overcrowded subway... and I guess it will remain so until the Olympics... And I wonder which of the two subways will be used - the crowded one or the extremely crowded one. I hope the new platforms will be work of art - otherwise they would not worth the change! |
#9
|
|||
|
|||
Stratford DLR
On Mar 31, 2:24 am, "alex_t" wrote:
Great! So now instead of same platform interchange with Central line (as currently) or dedicated footbridge (as was planned) there will be inconvenient two stairs interchange through existing overcrowded subway... and I guess it will remain so until the Olympics... And I wonder which of the two subways will be used - the crowded one or the extremely crowded one. I hope the new platforms will be work of art - otherwise they would not worth the change! Right.... Seriously, I doubt that the loss of the same-level interchange with the westbound Central Line is that great a hardship compared to the vast improvement in service levels, passenger comfort and station integration that will be accomplished with the opening of the new high- level DLR terminus. I would understand your concern if same-level interchange was available to both directions of the Central, but in this case I don't think it's that great a problem. |
#10
|
|||
|
|||
Stratford DLR
Improvement in service levels? The line is still one track to the Bow Road - how can there be any serious improvements? And besides, it makes my life more difficult - so I need to rant about it vbg |
Reply |
|
Thread Tools | Search this Thread |
Display Modes | |
|
|
Similar Threads | ||||
Thread | Forum | |||
Stratford Regional-Stratford Intl on DLR | London Transport | |||
NLL Closure / DLR to Stratford International | London Transport | |||
Stratford DLR | London Transport | |||
TfL Board gives approval for next step for DLR Stratford extension | London Transport | |||
DLR or Jubilee line extension to Stratford International - two questions | London Transport |