I see there are replacement buses running from Bow Church to Stratford this
weekend, is this a sign of progress on the new platforms, or just normal
maintenance? The first new platform was supposed to open in January this
year...

Paul S



  #2   Report Post  
Old March 5th 07, 02:47 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Oct 2004
Posts: 183
Default Stratford DLR

In ,
Paul Scott typed:

I see there are replacement buses running from Bow Church to
Stratford this weekend, is this a sign of progress on the new
platforms, or just normal maintenance? The first new platform was
supposed to open in January this year...



http://www.tfl.gov.uk/dlr/service_in...1_100307.shtml

Buses replace trains between Stratford and Bow Church

Due to engineering works for the construction of a new DLR station at
Stratford.

From 10/03/2007 until 11/03/2007

The replacement bus service will operate to Stratford, Pudding Mill Lane
and Bow Church stations, at a 10 minute frequency.


A ticket valid on DLR is required before boarding the bus. Mobility
impaired passengers who cannot use the replacement bus service are
advised to call 020 7363 9700 for further advice.

All other routes will be operating during this closure.

For further information pick up a leaflet or call DLR Customer Services
on 020 7363 9700. For advice on alternative routes during this
disruption call 020 7222 1234 or use Journey Planner.

Passengers travelling on the affected route are advised to allow extra
time for their journey. We apologise for any inconvenience.





--
Bob


  #3   Report Post  
Old March 5th 07, 02:52 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Nov 2004
Posts: 2,029
Default Stratford DLR


"Bob Wood" wrote in message
...

I see there are replacement buses running from Bow Church to
Stratford this weekend, is this a sign of progress on the new
platforms, or just normal maintenance? The first new platform was
supposed to open in January this year...



http://www.tfl.gov.uk/dlr/service_in...1_100307.shtml


That's what I saw earlier - just wondering what the actual work involved was
ging to involve - not 'normal maintenance' obviously...

Paul


  #4   Report Post  
Old March 5th 07, 03:35 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Jul 2003
Posts: 222
Default Stratford DLR

On Mar 5, 3:52 pm, "Paul Scott"
wrote:
"Bob Wood" wrote in message

...



I see there are replacement buses running from Bow Church to
Stratford this weekend, is this a sign of progress on the new
platforms, or just normal maintenance? The first new platform was
supposed to open in January this year...


http://www.tfl.gov.uk/dlr/service_in...1_100307.shtml


That's what I saw earlier - just wondering what the actual work involved was
ging to involve - not 'normal maintenance' obviously...

Paul


This is the second closure of this kind that I am aware of. The other
was (I think) some time before Christmas. On that occasion I could
see they had carried out works on the ground and on the existing
track, presumably to get the alignment and levels right, at the place
where the tracks to the new platforms will deviate from the current
route.

  #5   Report Post  
Old March 30th 07, 03:42 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Jul 2003
Posts: 222
Default Stratford DLR

On Mar 5, 4:24 pm, "Paul Scott"
wrote:
I see there are replacement buses running from Bow Church to Stratford this
weekend, is this a sign of progress on the new platforms, or just normal
maintenance? The first new platform was supposed to open in January this
year...

Paul S


The updated TfL website now says (hidden away in the DLR 'about'
section) the first of the new platforms is due to open in April 2007.
Track is now in place on both new platform roads but not yet connected
to the main line. It looks like there is still a lot of work to do on
the canopies etc but another DLR closure is scheduled over Easter.



  #6   Report Post  
Old March 30th 07, 05:19 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Sep 2006
Posts: 295
Default Stratford DLR


The updated TfL website now says (hidden away in the DLR 'about'
section) the first of the new platforms is due to open in April 2007.
Track is now in place on both new platform roads but not yet connected
to the main line. It looks like there is still a lot of work to do on
the canopies etc but another DLR closure is scheduled over Easter.


I think the canopies are mostly ready - the real work now is in
competition of the rail track and connection to the station. There was
footbridge to the Central line platform planned, but since it wasn't
even started so far, I think they dropped it from the project :-(

  #7   Report Post  
Old March 30th 07, 06:19 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Aug 2004
Posts: 341
Default Stratford DLR

On Mar 30, 6:19 pm, "alex_t" wrote:
I think the canopies are mostly ready - the real work now is in
competition of the rail track and connection to the station. There was
footbridge to the Central line platform planned, but since it wasn't
even started so far, I think they dropped it from the project :-(


And replaced it with a level connection to the new westbound Central
Line platform currently under discussion as part of the partial
reconstruction of Stratford Regional to cater for the Stratford
International branch of the DLR and the new NLL platforms north of the
GEML.

  #8   Report Post  
Old March 31st 07, 01:24 AM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Sep 2006
Posts: 295
Default Stratford DLR


And replaced it with a level connection to the new westbound Central
Line platform currently under discussion as part of the partial
reconstruction of Stratford Regional to cater for the Stratford
International branch of the DLR and the new NLL platforms north of the
GEML.


Great! So now instead of same platform interchange with Central line
(as currently) or dedicated footbridge (as was planned) there will be
inconvenient two stairs interchange through existing overcrowded
subway... and I guess it will remain so until the Olympics... And I
wonder which of the two subways will be used - the crowded one or the
extremely crowded one. I hope the new platforms will be work of art -
otherwise they would not worth the change!

  #9   Report Post  
Old March 31st 07, 07:21 AM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Aug 2004
Posts: 341
Default Stratford DLR

On Mar 31, 2:24 am, "alex_t" wrote:
Great! So now instead of same platform interchange with Central line
(as currently) or dedicated footbridge (as was planned) there will be
inconvenient two stairs interchange through existing overcrowded
subway... and I guess it will remain so until the Olympics... And I
wonder which of the two subways will be used - the crowded one or the
extremely crowded one. I hope the new platforms will be work of art -
otherwise they would not worth the change!


Right....

Seriously, I doubt that the loss of the same-level interchange with
the westbound Central Line is that great a hardship compared to the
vast improvement in service levels, passenger comfort and station
integration that will be accomplished with the opening of the new high-
level DLR terminus.

I would understand your concern if same-level interchange was
available to both directions of the Central, but in this case I don't
think it's that great a problem.

  #10   Report Post  
Old March 31st 07, 12:40 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Sep 2006
Posts: 295
Default Stratford DLR


Improvement in service levels? The line is still one track to the Bow
Road - how can there be any serious improvements?

And besides, it makes my life more difficult - so I need to rant about
it vbg



Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Stratford Regional-Stratford Intl on DLR Mark Morton London Transport 7 April 8th 10 03:31 PM
NLL Closure / DLR to Stratford International Paul Corfield London Transport 32 November 25th 06 12:05 AM
Stratford DLR John Rowland London Transport 1 December 28th 05 03:02 PM
TfL Board gives approval for next step for DLR Stratford extension Stevie London Transport 57 June 6th 05 10:08 AM
DLR or Jubilee line extension to Stratford International - two questions Bob Robinson London Transport 7 May 4th 04 10:43 PM


All times are GMT. The time now is 11:06 AM.

Powered by vBulletin®
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 London Banter.
The comments are property of their posters.
 

About Us

"It's about London Transport"

 

Copyright © 2017