On Apr 25, 7:42 pm, Matthew P Jones wrote:
I noticed today what appeared to be new connections from the fast lines
to the slow lines just south of where the Met line splits into the
Watford and Rickmansworth routes/ There is already such a connection
forming part of the existing junction.

Anyone know what is going on? Are the connections permanent, are they
re modelling the junction?


The junction is being remodelled, mainly to remove the moveable angles
in the fast/slow convergence and to replace otherwise worn-out track
and pointwork.

  #2   Report Post  
Old April 26th 07, 05:20 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Dec 2006
Posts: 173
Default New Connection Watford Triangle - Metropolitan Line

On Apr 26, 10:50 am, TheOneKEA wrote:
On Apr 25, 7:42 pm, Matthew P Jones wrote:

I noticed today what appeared to be new connections from the fast lines
to the slow lines just south of where the Met line splits into the
Watford and Rickmansworth routes/ There is already such a connection
forming part of the existing junction.


Anyone know what is going on? Are the connections permanent, are they
re modelling the junction?


The junction is being remodelled, mainly to remove the moveable angles
in the fast/slow convergence and to replace otherwise worn-out track
and pointwork.




The New (Southern) Watford South Junction, was started during the
Easter Shutdown.
It is scheduled to be commissioned during the Summer. Also I believe
(but dont have the dates to hand but they should be on the TfL
website) that there will be a number of weekday shutdowns Harrow/
Northwood-Amersham/Chesham/Watford and Marylebone-Great Missenden.

Also the first site to be moved out of the Signal Cabins is Watford,
controlled by Rickmansworth Signal Cabin is May 2009 and Amersham to
close completely later in 2009.

  #3   Report Post  
Old April 26th 07, 06:09 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Aug 2003
Posts: 71
Default New Connection Watford Triangle - Metropolitan Line


"chunky munky" wrote in message
ps.com...


The New (Southern) Watford South Junction, was started during the
Easter Shutdown.
It is scheduled to be commissioned during the Summer. Also I believe
(but dont have the dates to hand but they should be on the TfL
website) that there will be a number of weekday shutdowns Harrow/
Northwood-Amersham/Chesham/Watford and Marylebone-Great Missenden.


Interesting... the current PDF on the TFL site for the next 6 months
track closures makes no mention of any weekday closures on the met.
see
http://www.tfl.gov.uk/tfl/livetravel...k-closures.pdf




  #4   Report Post  
Old April 26th 07, 08:34 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Oct 2004
Posts: 947
Default New Connection Watford Triangle - Metropolitan Line

Matt Wheeler ) gurgled happily, sounding much
like they were saying :

The New (Southern) Watford South Junction, was started during the
Easter Shutdown.
It is scheduled to be commissioned during the Summer. Also I believe
(but dont have the dates to hand but they should be on the TfL
website) that there will be a number of weekday shutdowns Harrow/
Northwood-Amersham/Chesham/Watford and Marylebone-Great Missenden.


Interesting... the current PDF on the TFL site for the next 6 months
track closures makes no mention of any weekday closures on the met.
see
http://www.tfl.gov.uk/tfl/livetravel...k-closures.pdf


Early shutdown, late start, I presume?

I dread to think how many TfL managers'll be dangling from trees if they DO
try and shut the line down on weekdays...

Not having trains for half of all weekends across nine months or so is
farcical enough...
  #5   Report Post  
Old April 26th 07, 10:44 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Feb 2005
Posts: 1,150
Default New Connection Watford Triangle - Metropolitan Line

On 26 Apr 2007 20:34:57 GMT, Adrian wrote:

The New (Southern) Watford South Junction, was started during the
Easter Shutdown.
It is scheduled to be commissioned during the Summer. Also I believe
(but dont have the dates to hand but they should be on the TfL
website) that there will be a number of weekday shutdowns Harrow/
Northwood-Amersham/Chesham/Watford and Marylebone-Great Missenden.


Interesting... the current PDF on the TFL site for the next 6 months
track closures makes no mention of any weekday closures on the met.
see
http://www.tfl.gov.uk/tfl/livetravel...k-closures.pdf


Early shutdown, late start, I presume?

I dread to think how many TfL managers'll be dangling from trees if they DO
try and shut the line down on weekdays...

Not having trains for half of all weekends across nine months or so is
farcical enough...


Especially after the Met shutdowns for the Wembley Park upgrade not so
long ago. What was that, every weekend for 12+ months?


  #6   Report Post  
Old April 27th 07, 11:26 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Aug 2005
Posts: 38
Default New Connection Watford Triangle - Metropolitan Line


"chunky munky" wrote in message
ps.com...
On Apr 26, 10:50 am, TheOneKEA wrote:
On Apr 25, 7:42 pm, Matthew P Jones wrote:

I noticed today what appeared to be new connections from the fast lines
to the slow lines just south of where the Met line splits into the
Watford and Rickmansworth routes/ There is already such a connection
forming part of the existing junction.


Anyone know what is going on? Are the connections permanent, are they
re modelling the junction?


The junction is being remodelled, mainly to remove the moveable angles
in the fast/slow convergence and to replace otherwise worn-out track
and pointwork.




The New (Southern) Watford South Junction, was started during the
Easter Shutdown.
It is scheduled to be commissioned during the Summer. Also I believe
(but dont have the dates to hand but they should be on the TfL
website) that there will be a number of weekday shutdowns Harrow/
Northwood-Amersham/Chesham/Watford and Marylebone-Great Missenden.


I know a little about this project a few dates for anyone intrested

7 July - Finish south junction track work - The Kirow crane will return to
lift the main pannels currently sitting aroung Croxley Tip and the triangle
10 August - Renew Watford North Junction (closest to Ricky) (it is currently
sitting next to it)
17 August - Renew Watford East Junction (Croxley side)
24 August (Bank Holiday) - South Junction Prep works mainly point machine
fitting
31 August - Signalling commisioning
7 Sept + most Sept weekends track rewal on the curve between Croxley moor
park and removal exixitng junction.

Anyone wanting more details I could go on for pages
Andrew


  #7   Report Post  
Old April 28th 07, 05:53 AM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Jan 2005
Posts: 63
Default New Connection Watford Triangle - Metropolitan Line

On Apr 28, 12:26�am, "Andy" wrote:
"chunky munky" wrote in message

ps.com...





On Apr 26, 10:50 am, TheOneKEA wrote:
On Apr 25, 7:42 pm, Matthew P Jones wrote:


I noticed today what appeared to be new connections from the fast lines
to the slow lines just south of where the Met line splits into the
Watford and Rickmansworth routes/ *There is already such a connection
forming part of the existing junction.


Anyone know what is going on? *Are the connections permanent, are they
re modelling the junction?


The junction is being remodelled, mainly to remove the moveable angles
in the fast/slow convergence and to replace otherwise worn-out track
and pointwork.


The New (Southern) Watford South Junction, was started during the
Easter Shutdown.
It is scheduled to be commissioned during the Summer. Also I believe
(but dont have the dates to hand but they should be on the TfL
website) that there will be a number of weekday shutdowns Harrow/
Northwood-Amersham/Chesham/Watford and Marylebone-Great Missenden.


I know a little about this project a few dates for anyone intrested

7 July - Finish south junction track work - The Kirow crane will return to
lift the main pannels currently sitting aroung Croxley Tip and the triangle
10 August - Renew Watford North Junction (closest to Ricky) (it is currently
sitting next to it)
17 August - Renew Watford East Junction (Croxley side)
24 August (Bank Holiday) - South Junction Prep works mainly point machine
fitting
31 August - Signalling commisioning
7 Sept + most Sept weekends track rewal on the curve between Croxley moor
park and removal exixitng junction.

Anyone wanting more details I could go on for pages
Andrew



Carry on, I'm interested!

John Burke
WRUG

  #8   Report Post  
Old April 28th 07, 02:49 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Aug 2005
Posts: 38
Default New Connection Watford Triangle - Metropolitan Line


"burkey" wrote in message
oups.com...
On Apr 28, 12:26?am, "Andy" wrote:
"chunky munky" wrote in message

ps.com...





On Apr 26, 10:50 am, TheOneKEA wrote:
On Apr 25, 7:42 pm, Matthew P Jones wrote:


I noticed today what appeared to be new connections from the fast
lines
to the slow lines just south of where the Met line splits into the
Watford and Rickmansworth routes/ There is already such a connection
forming part of the existing junction.


Anyone know what is going on? Are the connections permanent, are they
re modelling the junction?


The junction is being remodelled, mainly to remove the moveable angles
in the fast/slow convergence and to replace otherwise worn-out track
and pointwork.


The New (Southern) Watford South Junction, was started during the
Easter Shutdown.
It is scheduled to be commissioned during the Summer. Also I believe
(but dont have the dates to hand but they should be on the TfL
website) that there will be a number of weekday shutdowns Harrow/
Northwood-Amersham/Chesham/Watford and Marylebone-Great Missenden.


I know a little about this project a few dates for anyone intrested

7 July - Finish south junction track work - The Kirow crane will return to
lift the main pannels currently sitting aroung Croxley Tip and the
triangle
10 August - Renew Watford North Junction (closest to Ricky) (it is
currently
sitting next to it)
17 August - Renew Watford East Junction (Croxley side)
24 August (Bank Holiday) - South Junction Prep works mainly point machine
fitting
31 August - Signalling commisioning
7 Sept + most Sept weekends track rewal on the curve between Croxley moor
park and removal exixitng junction.

Anyone wanting more details I could go on for pages
Andrew



Carry on, I'm interested!

John Burke
WRUG


The junction is being moved to allow quicker is the speed on the through
routes. The speed of the curve between Croxley and Moor park will go up to
30 currently 20. It should be the first journey time reduction on SSL in a
long time. It will also remove the 30mph speed restriction in both
directions on the main between Ricky and Moor Park. One of the main reasons
for the project is the moveable angles (or switch diamonds) that form part
of the current south to south crossover. They are very unreliable and
expensive to maintain so this should be a win win sistuation.
It will all be tradional LUL signalling no Westinghouse computers yet. There
will visable signallling changes in the run to August with a couple of new
post for new juction signals and related repeaters.
One thing I did not mention is that the route between Rickmansworth and
Croxley will be closed 10 August to 3 September mainly to allow the
pre-building of the new East junction on the curve. I guess this will have
some effect on first/last trains.
Andy


  #9   Report Post  
Old April 28th 07, 08:59 AM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Oct 2005
Posts: 130
Default New Connection Watford Triangle - Metropolitan Line




I know a little about this project a few dates for anyone intrested

7 July - Finish south junction track work - The Kirow crane will return to
lift the main pannels currently sitting aroung Croxley Tip and the triangle
10 August - Renew Watford North Junction (closest to Ricky) (it is currently
sitting next to it)
17 August - Renew Watford East Junction (Croxley side)
24 August (Bank Holiday) - South Junction Prep works mainly point machine
fitting
31 August - Signalling commisioning
7 Sept + most Sept weekends track rewal on the curve between Croxley moor
park and removal exixitng junction.

Anyone wanting more details I could go on for pages
Andrew


Thanks for the Info Andy, can you comment on the rumor that only 40% of
the scheduled work was completed during the massive easter shutdown?
  #10   Report Post  
Old April 28th 07, 02:25 PM posted to uk.transport.london
external usenet poster
 
First recorded activity at LondonBanter: Aug 2005
Posts: 38
Default New Connection Watford Triangle - Metropolitan Line


"www.waspies.net" wrote in message
...



I know a little about this project a few dates for anyone intrested

7 July - Finish south junction track work - The Kirow crane will return
to lift the main pannels currently sitting aroung Croxley Tip and the
triangle
10 August - Renew Watford North Junction (closest to Ricky) (it is
currently sitting next to it)
17 August - Renew Watford East Junction (Croxley side)
24 August (Bank Holiday) - South Junction Prep works mainly point machine
fitting
31 August - Signalling commisioning
7 Sept + most Sept weekends track rewal on the curve between Croxley moor
park and removal exixitng junction.

Anyone wanting more details I could go on for pages
Andrew

Thanks for the Info Andy, can you comment on the rumor that only 40% of
the scheduled work was completed during the massive easter shutdown?


About 75% of the work was complete. From what I understand LUL were overly
worried about an overun especially with the RMT about to dig there heels in
so the job was descoped. The new south to south was complted and the start
of the north to north and most the related plain line. The July 7th was pre
booked for plain line renewal so both jobs will happen that weekend.
Andy




Reply
Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules

Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Metropolitan line Watford John Leach London Transport 13 January 11th 17 11:16 AM
London Metropolitan line Watford [email protected] London Transport 33 December 30th 16 09:03 AM
M11 or A1 easiest tube connection for Heathrow weeyin London Transport 8 January 21st 15 03:06 PM
Cirlce Line Reverts to Circle / New Metropolitan Stock CJB London Transport 23 June 28th 10 09:11 PM
The London Underground and its South African connection CJB London Transport 13 January 14th 10 09:23 PM


All times are GMT. The time now is 01:46 PM.

Powered by vBulletin®
Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Copyright ©2004-2024 London Banter.
The comments are property of their posters.
 

About Us

"It's about London Transport"

 

Copyright © 2017